Planning is underway to begin the construction of a sidewalk along the south side of Sunrise Valley Drive and west of Reston Parkway.

The roughly half a-million-dollar project is expected to improve pedestrian connectivity near the future Reston Town Center Metro Station, which is expected to open sometime in the spring of next year.

The Fairfax County Board of Supervisors is considering an agreement to fund the project at a meeting today. The project was recommended in the Reston Area Metrorail Station Access Group study, which endeavored to ensure ample pedestrian connectivity and walkability to and from Metro stations in the area.

The agreement would be made with the Metropolitan Washington Airports. Authority.

MWAA has already constructed a contractor for the sidewalk project. Last year, the county already completed the first phase of the project from Glade Drive to just east of the Reston Association entrance.

If the agreement is approved this week, MWAA expects the project to take roughly four months to complete.

“There are no anticipated delays to Phase 2 of the Silver Line with the inclusion of this work,” according to a Dec. 7 staff memo.

0 Comments

The 11.5-mile extension of the Silver Line into Loudoun County has cleared another major hurdle.

Contractors have finally completed the rail yard associated with the multibillion-dollar project, according to the Metropolitan Washington Airports Authority.

The announcement comes a little less than a month after most of the work on the phase two extension had been completed. The transportation project would bring the Silver line from Reston into Loudoun County with six new stations.

Metro has not yet announced when phase two trains will begin to run. But a tentative date of spring 2022 is under consideration. The transit agency will manage and operate the rail line.

MWAA is currently overseeing the construction of the delayed project, which will be handed off to Metro. The project has been marred by delays and construction-related issues.

The 90-acre rail yard and maintenance facility is located at Dulles International Airport.

John Potter, president and CEO of the MWAA, said that substantial completion of the rail yard is a “critical” step to complete the extension project.

“We are now one step closer to making that happen,” Potter wrote in a statement.

The rail yard contains facilities that enable trains to complete maintenance and pairs, along with providing storage for trains, spare parts, and maintenance. The facility can store 184 rail cars.

Phase two was first scheduled to finish off in 2019. Contractor issues, flawed materials, defective panels, bad concrete, and other issues have resulted in years of delays.

Photo via MWAA

0 Comments

With Silver Line Phase 2 finally reaching substantial completion, the clock has started ticking on when the line will actually open to riders.

Late last week, Metropolitan Washington Airports Authority (MWAA) announced the completion of major construction on the long-delayed multi-billion dollar transportation project that will extend the Silver Line from Reston into Loudoun County with six new stations.

“This is a significant step toward completing the 11.5-mile extension that will provide rail service for residents in Reston, Herndon and eastern Loudoun County and give Metro riders direct access to Dulles Airport,” wrote Jack Potter, MWAA’s president and CEO, in last week’s press release.

This comes about two weeks after work was completed to tie the two Silver Line phases together and the connection of the Automatic Train Control System.

However, the project has not been handed over to Washington Metropolitan Area Transit Authority (WMATA) just yet, an authority spokesperson confirmed to Reston Now.

“Metro looks forward to entering the next phase of the project, during which we will perform hundreds of tests to ensure the extension can be operated safely and reliably before the Board accepts ownership and sets an opening date,” they wrote. “Metro takes full ownership only after the operational readiness evaluation and pre-revenue activities are satisfactorily completed.”

While this is fully expected and doesn’t necessarily impact the timeline for the line’s opening to riders, there are several steps that still need to happen prior to the handover.

First, Metro’s set to conduct about 200 safety tests with any necessary repairs being made. At the same time, Metro’s safety oversight body – Washington Metrorail Safety Commission – will start the certification that the line is safe.

Additionally, the railyard needs to be completed before Metro takes over the project. It currently remains unfinished, both WMATA and MWAA spokespeople confirmed to Reston Now. Hensel Phelps is the contractor for that portion of the project.

When testing, repairs, certification, and the railyard all are done, the Metro Board will vote to take “provisional control” of the project. After that happens, WMATA will set a date to launch passenger service and will begin employee training, simulations, and emergency drills.

In total, this all should take about six months, meaning that a tentative date for opening could be May 2022.

“We’re not projecting an opening date. [It is] dependent on many factors, and the Board will ultimately make that determination,” wrote a WMATA spokesperson.

In the meantime, the public can expect to see more trains running on the line, according to MWAA, as there’ll be a significant increase in testing in the coming months.

While months remain before passengers can catch a ride to Herndon or Ashburn, substantial completion marks a significant milestone for the long-delayed project.

“This is a major step in bringing passenger rail service to Dulles Airport and beyond. And as our residents know well, rail to Dulles has been years in the making,” Hunter Mill District Supervisor (and alternate on the Metro Board) Walter Alcorn wrote in a statement to Reston Now. “The progress of this phase of the Silver Line is made possible by Dulles Toll Road users and landowners who funded most of the project and have waited patiently for this day. I look forward to all parties working together to initiate passenger service during the coming months.”

In September, both Alcorn and Fairfax County Board of Supervisors Chairman Jeff McKay expressed frustration about the project’s constant delays and missed deadlines.

McKay appeared to reiterate his frustration in a statement to Reston Now.

“This is great news from WMATA this week. While the work was still incredibly behind and WMATA has a lot to do to rebuild trust with customers, I’m happy to see that significant [progress] has been made so we can fully open the Silver Line soon,” wrote McKay.

Initially, Silver Line Phase 2 construction was scheduled to be completed in 2018. But contractor issues, design changes, flawed materials, defective panels, and bad concrete all led to the years-long hold up which has tested the patience and viability of local businesses near the stations.

This past week’s good news also comes at a challenging time for Metro, as reduced service continues due to the pulling of 60% of its fleet in response to last month’s derailment.

0 Comments

(Updated, Nov. 9) After years of delays, Metropolitan Washington Airports Authority (MWAA) has announced that it has reached substantial completion on Silver Line Phase 2.

The announcement came Thursday afternoon and nearly two weeks after the successful tie-in of the two lines at the Wiehle-Reston East Metro station

MWAA is preparing to hand over the $2.8 billion public transportation project to Washington Metropolitan Area Transit Authority (WMATA). Metro currently owns the project and still has sole responsibility for the project until Metro assumes ownership.

WMATA has confirmed to Reston Now that the agency will still need about six months to complete testing and pre-revenue preparations before opening to riders. However, they are not yet setting an official opening date.

“Metro looks forward to entering the next phase of the project, during which we will perform hundreds of tests to ensure the extension can be operated safely and reliably before the Board accepts ownership and sets an opening date,” writes a WMATA spokesperson to Reston Now.

If that six month timeline does remain accurate, Silver Line Phase 2 should open to riders in May 2022.

From MWAA’s press release:

Silver Line Phase 2 Reaches Major Milestone

Metropolitan Washington Airports Authority officials announced Thursday they have declared substantial completion for work by Capital Rail Constructors (CRC) on Phase 2 of the Metrorail Silver Line extension project. The work by CRC, a joint venture led by Clark Construction Group and Kiewit, is a key component of the project to extend the region’s Metrorail public transit system to Dulles International Airport and beyond.

Substantial Completion means major construction is complete and allows operational readiness testing to begin, during which the contractor will demonstrate the project’s functionality, as a key step toward delivering the new rail line to the Washington Metropolitan Area Transit Authority, which operates the Metrorail system.

“This is a significant step toward completing the 11.5-mile extension that will provide rail service for residents in Reston, Herndon and eastern Loudoun County and give Metro riders direct access to Dulles Airport,” said Jack Potter, president and CEO of the Airports Authority. “In addition to providing new public transportation options, the Silver Line is a major catalyst for jobs and economic development in the National Capital region.”

The project also includes a 90-acre rail maintenance yard at Dulles International Airport, being built by Hensel Phelps, which is also nearing completion under a separate contract.

Phase 1 of the Silver Line opened in 2014, extending Metrorail service from East Falls Church to the eastern edge of Reston and triggering major transformations in the Tysons Corner and Wiehle Avenue areas. Those same trends are beginning along Phase 2, with changes already underway along the Dulles Corridor in Reston, Herndon and Ashburn, and at Dulles International Airport. The Silver Line’s goal is to help ease traffic congestion by providing alternative routes and easier commuting times, access to regional entertainment, shopping and Dulles Airport.

In a statement, contractor Capital Rail Constructors calls this a “significant milestone.” Here’s more from Keith Couch, the company’s project director:

“After successful Phase 1 and Phase 2 tie-in testing at Wiehle Avenue, MWAA has approved substantial completion of the Package A Silver Line Phase 2 project. The project will now move into Operational Readiness Testing, which will be completed by MWAA and WMATA. This significant milestone is a testament to the hard work, dedication, and collaboration of the project team and stakeholders. The CRC team is proud to have been a part of this transformational piece of infrastructure for the region.”

0 Comments
First Silver Line train pulls in to Wiehle-Reston East/Credit: Mike Heffner, Vita Images

(Updated, 3:50 p.m.) Work to tie-in Silver Line Phase 2 to Phase 1 was completed this past weekend, a Metropolitan Washington Airports Authority (MWAA) spokesperson tells Reston Now.

“The tie-in was a success and the Automatic Train Control System has been connected,” says spokesperson Marcia McAllister.

The work nessicated a shutdown of the Wiehle-Reston East Metro station.

One of the main goals was to finish the automatic train control system and it was completed, says McAllister. Additionally, signal infrastructure tests were done and those are still being reviewed.

There remains one or items that need to be finished, but those items can be completed without service outages, says McAllister.

However, MWAA is not committing to a date or specific timeframe for substantial completion and for when the $2.8 billion public transportation project could be handed over to Washington Metropolitan Area Transit Authority (WMATA).

“We are now following procedures set forth in the contract so we can move forward with what needs to be done to keep this project moving forward,”​ wrote McAllister when asked about a specific timetable.

In September, WMATA scheduled a weekend shutdown of Wiehle-Reston East Metro station in order to allow MWAA and the contractor Capital Rail Contractors (CRC) to connect the first and second phase of the Silver Line as well as perform tests related to signal infrastructure.

This work was crucial to keeping the opening of Silver Line Phase 2 on track and originally was supposed to be finished in June, but that didn’t happen as expected and necessitated a second shutdown.

All of this comes at a particularly fraught time for Metro as service has been drastically reduced to at least mid-November due to ongoing investigations into 7000-series cars related to the Blue Line train derailment in Arlington earlier this month.

Constant delays and missed deadlines on the multi-billion dollar Silver Line Phase 2 project have constantly frustrated residents, business owners, and government officials alike.

Recently, MWAA has continued to insist that substantial completion is coming soon, despite disagreements with the contractor on the timeline.

“The Airports Authority, WMATA and lead contractor Capital Rail Constructors worked together to make this a success,” reiterated McAllister.

Reston Now has reached to CRC about how the tie-in work this past weekend may impact their own assessment of a timeline for substantial completion, but have to yet to hear back as of publication.

Early last month, WMATA officials noted that it could be done and handed over to them in November.

However, there now seems to be some hedging on this timeline. At the Fairfax County Transportation Committee meeting at the end of September, it was announced that MWAA was “holding, at the moment, to the fourth quarter of 2021.”

A clearly-frustrated Hunter Mill District Supervisor Walter Alcorn responded at the meeting that it better be done prior to the Christmas holiday.

“Our next meeting of the transportation committee is December 14,” he said. “We better have substantial completion by then.”

0 Comments

As Silver Line Phase 2 slowly pulls into the station of completion, local officials are expressing their frustration at constant delays and missed deadlines.

In a brief update at yesterday’s (Sept. 28) Fairfax County Transportation Committee meeting, it was reiterated that Silver Line Phase 2 is expected to be substantially completed by the end of the year.

“In our discussions with [Metropolitan Washington Airports Authority], they are holding, at the moment, to the fourth quarter of 2021,” said Martha Elena Coello, special projects division chief for the Fairfax County Department of Transportation.

There are currently only two unresolved issues, according to a slideshow presented at the meeting, both of which are at the railyard and do not need to be resolved for substantial completion.

Hunter Mill District Supervisor Walter Alcorn said he was hopeful that meant MWAA would be handing over the project to Washington Metropolitan Area Transit Authority [WMATA] in late October, after the planned outage at Wiehle-East Reston Metro Station to tie-in the two lines. That work was supposed to be completed in June.

If the project does hit this new deadline, it would still be two months from a previous missed Labor Day deadline and years beyond the initial completion date.

Alcorn and others at the meeting showed their frustration at how Silver Line Phase 2 has been besieged by constant delays.

“This is four years overdue from the original date,” said Fairfax County Board of Supervisors Chairman Jeff McKay. “To not express some frustration here… would be a mistake. I think all of us are very frustrated.”

Alcorn also was noticeably exasperated at the pace of the project.

“Our next meeting of the transportation committee is December 14. We better have substantial completion by then,” he said.

In response, MWAA acknowledges the disappointment that many have about the delays.

“We understand the frustrations of everybody, elected officials and public alike,” MWAA spokesperson Marcia McAllister told Reston Now. “Our goal is to proceed with the [October] outage, evaluate the work that is done that weekend, and make decisions as soon as possible.”

McAllister also reiterated that MWAA is “holding on to fourth quarter 2021” as a timeline for substantial completion.

In multiple previous MWAA reports, it was revealed that there were significant disagreements between MWAA and the contractor Capital Rail Constructors (CRC) on the timeline.

While MWAA said it would be completed by the end of the year, CRC said spring 2022.

But now, CRC seems to be backing off their timeline, noting that increased collaboration with the authorities have quickened the pace.

“We are working together with MWAA and WMATA on coordinating and finalizing testing to target substantial completion of the Silver Line Phase 2A in Q4,” CRC project executive Keith Couch wrote in a statement to Reston Now.

Even if Silver Line Phase 2 is substantially completed by late October, as noted in the presentation provided to the committee, WMATA will still need approximately six months to complete testing, pre-revenue preparations, and to open the system to riders.

That could mean an opening date of April or May  2022.

The $2.8 billion public transportation project will include six new stations, extending Metro from Reston to Loudoun County.

It remains a potential game changer for the region, though many with financial investment connected to the project have grown understandably impatient.

“A lot of folks have contributed substianal money to making this happen,” said McKay at the transportation committee meeting. “And they are sitting here, waiting for service.”

0 Comments
Map of the impacted section of the Dulles Airport Access Highway (via MWAA)

Approximately seven miles of the Dulles International Airport Access Highway going westbound will be closed this weekend (Sept. 11 and 12) for maintenance work on pedestrian bridges.

Starting just east of Reston at mile marker 8.3, traffic will be diverted to the left lane of the Dulles Toll Road. Drivers will be able to enter the airport access road again at mile marker 1.7, near the Route 28 toll plaza and right past the soon-to-be-opened Innovation Center Station.

Ramps at mile marker 9 and 3.3 for the westbound portion of the airport access highway will also be closed.

The closures will run from 6 a.m. to 6 p.m. each day.

All work is weather-dependent, though weather does not appear it will be a factor this weekend.

This work is being done by contractor Capital Rail Constructors as part of its preparations for the opening of Silver Line Phase 2, a Metropolitan Washington Airport Authority official says.

A weekend was chosen to conduct the maintenance work in the hopes of minimizing the closure’s impact on traffic, the MWAA official notes.

Photo via MWAA

0 Comments
Wiehle-Reston East Garage (via Fairfax Connector)

The Wiehle-Reston East Metro station will be closed during the weekend of Oct. 23 and 24 so crews can work to connect the first and second phase of the Silver Line.

This will be the second time in six months that the station has been shut down so the two phases can be tied together after work and tests related to signal infrastructure were not completed in June as expected, necessitating another shutdown.

If the work is completed as hoped this time, it will be a major milestone for the $2.8 billion Silver Line Phase 2 project, potentially putting it on track for substantial completion by November.

The scheduled shutdown was added to Washington Metropolitan Area Transit Authority’s (WMATA) track work page shortly after officials delivered an update on the project to the WMATA board yesterday (Thursday).

Metropolitan Washington Airports Authority (MWAA) spokesperson Marcia McAllister said in an email to Reston Now that the scheduling of the shutdown for late October is “great news.”

“Now that a date has been set for the service outage needed to allow completion of the tie-in between Phase 1 and Phase 2 of the Silver Line, the Airports Authority and our contractors can get this essential work done in October and move the project toward substantial completion,” McAllister wrote.

Substantial completion refers to the point when MWAA will be ready to hand the project to WMATA. The authority previously set Labor Day weekend as the deadline but acknowledged in July that it wouldn’t meet that timeline.

At the board meeting, WMATA officials said they were comfortable with MWAA setting a new substantial completion deadline for the end of this year, stating that the work will most likely be finished in November.

If that is the case, Metro will still need another five to six months of operational readiness testing and pre-revenue activities, but that could mean the Silver Line Phase 2 will open to riders by May 2022.

However, in MWAA’s most recent monthly report, the project’s contractor Capital Rail Constructors proposed a substantial date of May 19, 2022, which could push the opening all the way to late 2022. It wasn’t the first time that the two parties disagreed on the project’s schedule.

Shortly after the report was released, though, CRC project executive Keith Couth told Reston Now that there were “opportunities through collaboration” to improve on that date and get it completed much sooner.

When reached for comment, Couch reiterated that they are working to finish by the end of this year.

“We are in the testing phase of the project which is very dependent on coordinating and finalizing testing with MWAA and WMATA, including scheduling of the next outage at Wiehle Avenue and the review of test reports,” Couch said. “In collaboration with MWAA and WMATA, we are working together to improve on the schedule, targeting a substantial completion in Q4.”

With the Wiehle shutdown now scheduled and the contractor supportive of a hoped-for 2021 substantial completion date, Silver Line Phase 2 is seemingly back on track after years of delays that have frustrated local officials, residents, and businesses alike.

“Level F” testing — meaning testing with actual trains — also began late last month and is going well, according to WMATA officials.

The nearly $3 billion project will extend Metro’s Silver Line from the Wiehle-Reston East station west to Ashburn in Loudoun County. In total, six new stations will be added, including one at Reston Town Center and two in Herndon.

Construction began back in 2014 and was originally supposed to finish in 2018.

Photo via Fairfax Connector

0 Comments

A newly proposed timeline for Silver Line Phase 2 pushes the date for substantial completion of the project to May 19, 2022, nearly one month later than previously suggested.

The date comes from contractor Capital Rail Constructors and was included in the Metropolitan Washington Airports Authority’s July monthly report, which was finished on Aug. 26 and released on Wednesday (Sept. 1).

Like before, MWAA says in its report that it disagrees with the contractor’s projected “longest path” timeline.

“Based on the remainder of work to be accomplished, the Airports Authority believes that the Substantial Completion date can be accomplished within Q4 2021,” the report says.

The business was contractually obligated to complete the project in August 2019, MWAA spokesperson Marcia McAllister said.

A phase known as Level F testing began this week and could last several weeks, she said. While components work on their own, this process helps ensure that the entire system works together.

“We are in the testing phase of the project, which is very dependent on coordinating and finalizing testing with MWAA and WMATA, including scheduling of the next outage at Wiehle Avenue and the review of test reports,” Keith Couch, project executive for Capital Rail Constructors, said in a statement.

The Wiehle-Reston East Metro station was shut down for a weekend in late June so workers could tie together the Silver Line’s first and second phases, but some tests were not completed over those two days, so another outage is needed.

WMATA says it typically provides information about planned track work about eight weeks in advance. As of today (Friday), no notice about a Wiehle station shutdown has been posted.

While the new timeline extends the substantial completion date from April 21 to May 19, Capital Rail Constructors suggested that the completion could shift to this year.

“While based on the information available at this time our schedule shows a May 2022 substantial completion date, there are opportunities through collaboration with MWAA and WMATA to improve on that date and complete the project by October of this year,” Couch said in the statement.

Matt Letourneau, a Loudoun County supervisor on the WMATA board of directors, said yesterday (Thursday) at a Northern Virginia Transportation Commission meeting that despite the contractor placing the substantial completion date into 2022, the Airports Authority has not changed its fall 2021 timeline.

The $2.8 billion project will extend Metro’s Silver Line from the Wiehle station westward to Ashburn in Loudoun County, adding six new stations along the Dulles Toll Road.

Substantial completion represents the moment when MWAA will be ready to hand the 23-mile extension over to the Washington Metropolitan Area Transit Authority. Officials previously expected Metro to take control of the project by Labor Day, but MWAA admitted in early July that it won’t make that deadline.

After the substantial completion, it will still take at least half a year before the line can begin operating publicly, since Metro needs to conduct its own testing, training, and other activities, a WMATA presentation in July noted.

Preliminary construction for Phase 2 began in 2014. It was originally supposed to open in 2018.

0 Comments

Morning Notes

Fairfax County Kids Return to School — “We are back, ready to experience all the great things that come with learning together, five days a week in person. We can’t wait to see our students arrive at school…Show off that first-day excitement by posting photos to your favorite social media site and tagging them with #FirstDayFairfax and #FCPSReturningStrong.” [FCPS]

MWAA Proposes New Tech on Dulles Toll Road — “The Metropolitan Washington Airports Authority wants to add digital signs and closed-circuit monitoring technology along the Dulles Toll Road. The airports authority is looking for a contractor to build the infrastructure and install an intelligent transportation system — which would include six dynamic message signs and 15 closed-circuit television installations — along the widely-used commuter route.” [Washington Business Journal]

W&OD Trail Near Wiehle Reopens After Utility Work — The Washington & Old Dominion Trail has reopened east of Wiehle Avenue in Reston after closing earlier this summer so Dominion Energy could relocate overhead electric transmission lines. The utility work was necessary to prepare the site for construction on a pedestrian bridge over Wiehle that’s expected to begin next summer. [The W&OD Trail/Twitter]

Virginia Leads in Rent Relief Funding After Past Stumbles — “From January through May, Virginia distributed more dollars than any other state from the first round of the Emergency Rental Assistance Program, according to U.S. Treasury figures. By the end of June, Virginia ranked second only to Texas…As of late July, Virginia has spent more than $335 million in rental relief funds and assisted more than 51,000 households, according to state figures.” [Associated Press/WTOP]

0 Comments

Morning Notes

A dog cools off under some greenery (via vantagehill/Flickr)

Reminder: Excessive Heat Watch Takes Effect Today — Fairfax County and the rest of the D.C. area will be under an Excessive Heat Watch from noon to 8 p.m. The heat index could reach 105 to 110 degrees Fahrenheit, so the National Weather Service advises drinking plenty of fluids, staying inside as much as possible, and checking up on neighbors and relatives. [NWS]

Hunters Woods Garden Thieves Resurface — Thieves that reportedly stole thousands of dollars in plants and other materials from two community garden plots at Hunters Woods Park in May have returned with the harvest season. Reston Association increased security around the gardens, including the installation of fencing and flood lights with sensors, but the culprits evidently have not been deterred from stealing vegetables. [Patch]

No Trespassing at Silver Line Phase 2 Stations — The Metropolitan Washington Airports Authority issued a reminder that, while Metro’s six impending Silver Line stations look finished, they are still closed “because of ongoing construction work and potential safety hazards.” MWAA maintains that they will “most likely” open in early 2022, but there is some conflict over the timeline with the project’s contractor. [Dulles Corridor Metrorail Project]

County Board Endorses Dog Park Study — The Fairfax County Park Authority Board gave its support on July 28 to a countywide dog park study that calls for at least one new park and highlights concerns about inattentive visitors, insufficient water, and surface conditions at existing parks. A draft version of the study came out in March, and the full, final report will become available next month. [FCPA]

Photo via vantagehill/Flickr

0 Comments

(Updated at 9:05 a.m. on 8/5/21) A new report reveals that there’s significant disagreement between the Metropolitan Washington Airports Authority (MWAA) and its contractor, Capital Rail Constructors (CRC), about when Silver Line Phase 2 is expected to be completed.

Released publicly yesterday (Aug 3), MWAA’s June monthly report on the project says that CRC is forecasting a substantial completion date of April 21, 2022 for the second phase of Metro’s Silver Line extension.

That is more than seven months after Labor Day 2021, when MWAA had hoped to hand over the project to Metro, though officials already admitted last month that they will miss that deadline.

However, in its monthly report, MWAA says it “disagrees” with the timeline laid out by CRC and believes the remaining work that needs to be completed “can be accomplished in significantly less time.”

The airports authority believes the work can be finished “within Q4 2021,” according to the report.

About six months is needed between substantial completion and for the system to open to complete testing and “pre-revenue activities,” according to a Metro presentation from last month.

This means that, if the project follows CRC’s timeline, Silver Line Phase 2 won’t officially open until late October 2022 at the earliest, a year-long delay compared to what was announced earlier in 2021.

Even MWAA’s preferred timeline would still push the start of service back to May or June 2022.

MWAA spokesperson Marcia McAllister says the authority remains “hopeful” that the contractor can complete the necessary work by the end of this year. She explained that both the contractor and MWAA make timeline estimates based on “their own knowledge base, but just come up with different results.”

“We will continue to work with them, talk to them, and encourage them to speed up the work they are doing,” McAllister said.

Keith Couch, project executive for Capital Rail Constructors, told Reston Now that the contractor group is open to discussing with MWAA about how to move the project quicker and get it done by late this year.

“We are in the testing phase of the project which is very dependent on coordinating and finalizing testing with MWAA and WMATA, including scheduling of the next outage at Wiehle Avenue and the review of test reports,” Couch wrote in a statement. “While based on the information available at this time our schedule shows an April 2022 substantial completion date, there are opportunities through collaboration with MWAA and WMATA to improve on that date and complete the project by later this year.”

One of the tasks that still needs to be completed is the full connection of Phase 2 to Silver Line Phase 1, which opened in 2014. The Wiehle-Reston East Metro station was shut down for a weekend in June so crews could work on the linkage, but the task wasn’t completed.

MWAA has said that an additional shutdown is needed to complete that work. Dates for that shutdown have yet to be announced.

McAllister says MWAA is working with the Washington Metropolitan Area Transit Authority to find dates that work for all, but the two agencies have yet to make a determination on when the second Wiehle station shutdown might happen.

According to MWAA’s monthly report, CRC has proposed a timeline where the Phase I integration work will be completed in October.

The timeline disagreement is another wrinkle in the long-running saga of the $2.8 billion public transportation project to extend Metro from Reston into Loudoun County with six new stations.

Many are growing impatient with the consistently-delayed Silver Line Phase 2, which originally was set to open in 2018.

“We really, really want to get this project done as soon as possible,” McAllister said. “We understand the community’s needs to have Silver Line Phase 2 open.”

0 Comments

Morning Notes

Lake Anne (via vantagehill/Flickr)

Fairfax County Gave Republican Governor Nominee Tax Break — “GOP gubernatorial nominee Glenn Youngkin and his wife last year successfully petitioned Fairfax County to designate their horse farm as an agricultural district, which led to a 95% reduction in the taxes they pay on the 31.5-acre property in Great Falls that surrounds their home.” [Richmond Times-Dispatch]

Material Costs Drive Up Silver Line Phase 2 Costs — “The Metropolitan Washington Airport Authority is having to pay an extra $20 million to cover the higher cost of materials needed to build the extension of Metro’s Silver Line…So far, the construction’s progress has eaten up $2.464 billion, but the airports authority maintains the [$2.778 billion] budget won’t change, thanks to contingency funds.” [Washington Business Journal]

County Redistricting Committee to Meet Next Week — Fairfax County’s 20-person Redistricting Advisory Committee will hold its first meeting on Tuesday (July 27) at 6 p.m. at the Fairfax County Government Center. Open to the public, the meeting will focus on legal requirements, equity, and bylaws as the group prepares to recommend new electoral boundaries for the county’s supervisor and school board districts. [Fairfax County Government]

Reston Hospital Hires New Executive — Allyssa Tobitt will serve as Reston Hospital Center’s new chief operating officer starting Aug. 2. Replacing Ben Brown, who moved to Dominion Hospital in West Falls Church, she worked at the corporate office of Reston Hospital’s parent company HCA Healthcare in Nashville, Tennessee as well as at hospitals in its for-profit health system near Miami and Tampa, Florida. [HCA]

Photo via vantagehill/Flickr

0 Comments
The Herndon Metro station (staff photo by Jay Westcott)

The Labor Day deadline for “substantial completion” of Silver Line Phase 2 won’t be met, Metro staff acknowledged at a Board of Directors safety and operations committee meeting today (Thursday).

The presentation confirmed what the Metropolitan Washington Airports Authority (MWAA) told Fairfax County earlier this month.

At this point, it remains unknown when the project will be substantially completed and able to be turned over to the Washington Metropolitan Area Transit Authority (WMATA). The expected delay will likely push the opening date even further back.

“There hasn’t been a new substantial completion day published [by MWAA],” said Andy Off, Metro’s vice president of project implementation and construction. “But we are confident it’s going to get moved past Labor Day.”

The latest delay of the $2.8 billion public transportation project stems from the need for more testing and work to tie Silver Line’s first and second phases together. That will require another shutdown of Wiehle-Reston East Metro station, much like the one that happened late last month.

“There are specific tests that were not completed over that weekend that necessitated a further shutdown,” Off said. “We are currently working with MWAA to schedule that.”

Reston Now reached out to MWAA about when that station shutdown will happen but has to hear back as of publication.

Off assured committee members that the delay has nothing to do with concrete issues or any other major safety concern.

“Right now, it’s really an IT project as it relates to our signal infrastructure,” Off said.

Once the Wiehle-Reston East outage gets scheduled and the work is completed, Off said there will be a better idea of a substantial completion date, with “fall” being as specific as he can get at this juncture.

Metro will need about six months from substantial completion to complete testing and “pre-revenue activities,” including trainings and further testing, which is contractually obligated to take no longer than 90 days, according to a presentation to Fairfax County Board of Supervisors transportation committee last month.

A Labor Day hand-off would have put Silver Line Phase 2 on track to open in the first quarter of 2022, but now, operations likely won’t begin until later that year. The project will extend Metro from Reston into Loudoun County with six new stations.

At the WMATA board committee meeting, officials emphasized that this delay is unrelated to any problem. There’s simply a need for more testing time.

“It’s not unusual to have several tests planned and just not have the amount of time as you need,” rail safety expert Devin Rouse, who’s on the Metro board, said. “If anything significant does come up, that’s a discussion we really need to have. At this point, this is normal for these types of projects.”

While officials have downplayed this particular delay, it follows a long line of Silver Line Phase 2 holdups that have frustrated residents and businesses waiting for the multi-billion-dollar public transporation project, which was initially set to open in 2018.

0 Comments

Morning Notes

Bob Simon statue through LOVE sign at Lake Anne Plaza (via vantagehill/Flickr)

PIVOT Grant Application Deadline Today — This is the last day for hotels, restaurants, and other local businesses affected by the pandemic to apply for COVID-19 relief funding from Fairfax County’s PIVOT grant program. The application portal will close at 11:59 p.m. [Fairfax County Government]

Pfizer Seeks Approval for COVID-19 Vaccine Booster — Pfizer will request authorization from the Food and Drug Administration for a third dose of its COVID-19 vaccine, which it says could boost immunity and help ward off variants if delivered within 12 months. Research suggests the Pfizer shot and other widely used COVID-19 vaccines offer strong protection against the highly contagious delta variant. [Associated Press/WTOP]

Expansion Proposed for Dulles Airport — The Metropolitan Washington Airports Authority is seeking environmental approval from Virginia to potentially build a new three-story, 535,000 square-foot concourse at Dulles International Airport to support United Airlines. The planned facilities would revamp a “temporary” hub that has been in use since the mid-1980s, but cost is a concern. [Airline Weekly]

Friday Night Live! Returns Tonight — After an unexpected cancellation last week, the Herndon summer concert series will kick off at 6:30 p.m. with Turtle Recall, a band made up of South Lakes High School alumni. Food vendors for this season include Jimmy’s Old Town Tavern, Dominos, and Egg Karne, and FNL has partnered with the local breweries Aslin and Mustang Sally Brewing. [Herndon Rocks]

Photo via vantagehill/Flickr

0 Comments
×

Subscribe to our mailing list