Afternoon Poll: Your Silver Line Opening Predictions

Metro SIlver Line Map/Credit: Metro

The Metropolitan Washington Airports Authority announced on Monday that the Silver Line Metro extension is not ready to take the next step towards an opening date.

MWAA had a 15-day period in which to review the work of its construction contractor, Virginia Transit Partners. MWAA found issues in 7 of 12 categories. Those issues must be fixed before MWAA can hand over the project to Metro, which will then have 90 days to conduct its own testing. It is not known how long it will take VTP to remedy the issues.

This is the third setback in recent months. Metro has never set an opening date, but the original handoff was estimated to happen in August for a December opening. Construction delays and testing issues pushed the handoff to November, and now to at least March.

Based on all that — and with chances that more issues can be found — when do you think the Silver Line, and its terminus at Wiehle-Reston East, will open?

 

Recent Stories

The Knutson Companies is thrilled to announce new opportunities for Loudoun County living with the release of a new section of rooftop terrace townhomes and a brand new community of…

Lake Anne Plaza in Reston (staff photo by James Jarvis) The Lake Anne Plaza summer concert series is making a comeback after a five-year break. Beginning on Wednesday, June 12,…

Fairfax County police vehicle with lights (file photo) A juvenile was arrested for allegedly abducting and raping an adult woman in Reston. The incident occurred just before 11:30 p.m. on…

A statue of Reston founder Robert E. Simon sits on a bench at Lake Anne Plaza (staff photo by Angela Woolsey) Reston is sort of an odd duck — an…

×

Subscribe to our mailing list