Will Glitchy Tracking Control Mean a Move To Human Control for Silver Line?

Metro SIlver Line Map/Credit: MetroUpgrading the faulty tracking control software for Metro’s Silver Line will cost $1.8 million and may take up to a year to replace,  but can the  train finally leave the station without it?

It remains to be seen whether Metro and Metropolitan Washington Airport Authority would delay the opening of the Silver Line — which is already months behind schedule — for that length of time. But on the other hand, the ATC system is crucial for a safe rail line. ATC failures were deemed responsible in the June 2009 Metro crash that killed the driver and eight passengers.

Officials said last week that the Silver Line may get up and running with the ATC that is in place now, but may have human operators working to ensure safety. In its approval of the contract to Alstom Signaling to provide the technology upgrade, MWAA said “WMATA (Metro) will provide “extra staffing at the Project’s expense to ensure reliability.”

MWAA officials have until next week to complete their review of Betchtel’s submission of “substantial completion” of the Silver Line’s 11-mile Phase 1. The $2.8 billion Phase 1 will run from East Falls Church to Reston’s Wiehle Avenue. 

Betchel’s Dulles Transit Partners, which built the project, originally submitted for substantial completion on Feb. 7, but MWAA said there were issues in 7 of 12 areas, including the ATC system. The ATC glitches were also responsible for one of several completion delays last fall. The project was originally (but unofficially) estimated to have its first riders by December 2013; the safe estimate now is by summer.

MWAA said Alstom is the only contractor able to provide the necessary equipment for the upgrades and that the upgrades will be paid from a $23 million Silver Line contingency fund. Citizens advocacy group Reston 2020 said that estimate is oversimplified.

“Of any extra costs MWAA agrees to pay WMATA for staffing, MWAA will actually pay only 4 percent of while Dulles Toll Road users will pay half under the inequitable ‘Funding Partners’ agreement.” Reston 2020 co-chair Terry Maynard writes on the group’s blog. “The rest will be paid by Fairfax and Loudoun counties.”

Meanwhile, Virginia Gov. Terry McAuliffe met with MWAA officials about the Silver Line on Tuesday, WTOP reports.

Recent Stories

Celebree School will have a grand opening for its new Herndon location on Saturday, April 27 (courtesy of Celebree School) A Maryland-based early childhood education company is opening a second…

W&OD Trail in Herndon (staff photo by James Jarvis) The Washington & Old Dominion (W&OD) Trail has reached the half-century mark. The Northern Virginia Regional Park Authority (NOVA Parks) is…

Left to right: Fairfax Alliance for Better Bicycling President Bruce Wright, Hunter Mill District Supervisor Walter Alcorn and Reston Bike Club Vice Chairman Joel Kuester team up to promote the…

Morning Notes

Heming, a mixed-use apartment building in Tysons, at sunset (staff photo by Angela Woolsey) FCPS Prevails in Sexual Assault Lawsuit — “A jury on Wednesday rejected a woman’s lawsuit seeking…

×

Subscribe to our mailing list