Metro Takes Silver Line Control, Moves Closer to Opening

Wiehle-Reston East Metro StationWashington Metropolitan Area Transit Authority (Metro) officially took possession of the Silver Line Tuesday morning, marking a significant milestone in the rail extension’s timeline towards opening this summer.

The handoff took place at 5:30 a.m., said Metro deputy general manager Rob Troup.

The opening of Phase 1, which will run from East Falls Church to Reston’s Wiehle Avenue, is more than six months behind its projected opening schedule, though neither Metro nor the Metropolitan Washington Transit Authority (MWAA) announced a firm opening date.

Operational readiness (ORD) means that MWAA, which built the $2.9 billion extension, is finished with its part and Metro can now begin a 90-day training and inspection period.

“We are very, very pleased to get to ORD,” Troup said in a conference call with reporters. “Service is going to be significant to the people in Northern Virginia.”

There was no announcement about when the line will be open for service, however.

“We feel we are in a very good position,” Troup said in response to a question about opening this summer. “We are working closely with MWAA, and they have allowed us to get our personnel in there early and we have done training for station managers [and other personnel].  I don’t want to give anything definitive. We may have to push [the opening] beyond if we find something of concern to us.

“But we are testing, hiring and training and feel we are in a very good position.”

Troup said there are a few small items that MWAA contractor Dulles Transit Services needs to address in the coming days. Among them: contract progress and paperwork; drainage systems in stations; and fencing work that needs to be finished.

The bobbing track issue and faulty station speakers have been fixed, Troup said.

Other news of note:

About a week prior to opening, there will be simulated rail service, where trains will run on their regular schedule. The simulated service will not include passengers. When the line opens, trains will run every six minutes during rush hour and every 12 to 20 minutes at other times.

Metro security has been working with local law enforcement (Fairfax County Police, Virginia State Police and Airport Authority Police) for a year, said Metro Transit Police Chief Ron Pavlik. Eight hundred first responders have been trained.

There will be two full-scale emergency exercises with law enforcement agencies, Fairfax County Fire Rescue, Virginia Department of Transportation and D.C. Department of Transportation, Pavlik said.

One will be a drill simulating a “real life scenario,” he said. The other will simulate an emergency on the aerial tracks near the Spring Hill station. The drills will likely occur on a weekend, but no date has been announced.

Recent Stories

Marc Smith will serve as the new Herndon economic development director starting in May (courtesy Town of Herndon) The Town of Herndon is getting a new director of economic development….

Morning Notes

Reston (staff photo by Scott Brodbeck) Demolition begins at burned hust of Oud Resto and Hall — “The site of the Main Street restaurant that burned down in 2020 is where…

OmBaked CBD Boutique at Lake Anne Plaza in Reston (staff photo by James Jarvis) OmBaked CBD Boutique at Lake Anne Plaza in Reston is hosting a holistic health fair next…

Morning Notes

Boaters and geese can be seen in the distance on Lake Accotink (staff photo by Angela Woolsey) Man fires gun at dog, Fairfax County police say — “Fairfax County Police…

×

Subscribe to our mailing list