Metro: If Work Gets Done, Opening Date Set Next Week

Wiehle-Reston East Metro Station

If Silver Line contractor Dulles Transit Partners finishes the work on the final “seven or eight” items this week, an opening date for service will be set on Monday, says Metro General Manager Richard Sarles.

“We are in the final stretch,” Sarles said in a call with reporters today.

A week ago, Metro Deputy General Manager Rob Troup said DTP, the Bechtel unit hired by Washington Metropolitan Airports Authority (MWAA) to build the 11-mile Phase 1 rail extension from East Falls Church to Reston’s Wiehle Avenue,  had only completed about half of the items that must be done before passengers can ride.

Metro obtained control of the Silver Line May 27, starting a 90-day testing and training period. However, MWAA and Metro agreed in April that certain items could be completed after the handover but before passenger service begins.

There has been at least one report that the Silver Line will begin service the last week of July. While the Silver Line is more than six months behind schedule, an opening date for service has never been set. Silver Line officials would not confirm the July speculation on Monday. However, that may turn out to be correct if progress is made this week.

“We have date we plan against, but when you set a firm date, it is based on progress you have made,” said Sarles. “If the is done [this week], my level of confidence will be high enough to establish a firm date for revenue operation.”

Among the items to be completed: obtaining certificates of occupancy; finishing painting tunnel handrails; testing of fiber optic cable; and testing of intrusion and fire alarms, said Sarles.

There will be a public safety drill on June 29 at the Spring Hill Station. There will also be a week of simulated service before passengers can ride the Silver Line.

Recent Stories

An encampment has taken shape in recent years near the Sunrise Assisted Living in Reston (staff photo by Fatimah Waseem) A tent encampment housing between 20 and 35 individuals in…

Fairfax County Courthouse (staff photo by James Jarvis) The Fairfax County Board of Supervisors is considering using kiosks equipped with artificial intelligence to provide select legal information in a variety…

Just a day after negotiations for a Washington Wizards and Capitals arena in Alexandria officially fell through, George Mason University has announced that it’s no longer planning to build a joint baseball and cricket stadium in Fairfax for the Washington Freedom.

Fox Mill Road in Herndon will be closed on April 1 (via VDOT) Fox Mill Road will be closed at the beginning of next month to allow for a pipe…

×

Subscribe to our mailing list