Progress Report: Lake Anne Dredging Ahead of Schedule

Lake Anne Dredging/Photo: Chesapeake ChocolatesReston Association says the dredging project at Lake Anne is running ahead of schedule and should be completed in two or three weeks.

Work has been completed in the coves and plaza areas, RA says. Dredging contractor Lake Services said a large section near the fountain is all that remains to be dredged.

Reston Association received a state permit last month to dredge Lake Anne. Areas to be dredged include the plaza area, the canal area, and coves near Inlet Court, Waters Edge, Waterview Cluster, South Shore, and the south boat ramp. See a map on RA’s website.

RA says residents’ boats no longer have to be moved for the remaining work to be finished.

RA is dredging the coves to clear accumulated sediment and leaf debris to improve boat and shoreline access. The project will also provide additional water storage areas and deeper areas for fish. Removing sediment at the coves where the major drainage ways enter the lake helps to prevent the lake from filling in with accumulated sediments, RA says.

Photo: Recent dredging near Lake Anne Plaza/Credit: Chesapeake Chocolates

Recent Stories

Morning Notes

Beaver munching on grass by Walney Pond in Chantilly (staff photo by Angela Woolsey) Shake Shack proposed for Kamp Washington Shopping Center — “Fairfax City Board of Architectural Review approved…

Taim Mediterranean Kitchen is officially open in Reston (Photo courtesy taim). Taim Mediterranean Kitchen in Reston has permanently closed just four months after its opening. The New York-based chain, known…

Morning Notes

Cat (staff photo by Vernon Miles) Cat declawing to be banned in Virginia — “Veterinarians will not be allowed to declaw cats in Virginia starting in July, unless there are certain…

The Knutson Companies is thrilled to announce new opportunities for Loudoun County living with the release of a new section of rooftop terrace townhomes and a brand new community of…

×

Subscribe to our mailing list