Lack of Training and Weight Limits Among Issues Found In Latest Metro Audit

A new audit from the Washington Metrorail Safety Commission has found a dozen items that Metro needs to correct as soon as possible and before the opening of Silver Line Phase 2.

Many of the items are related to the lack of guidance and training for employees on a new structural inspection manual. Additionally, the audit also says Metrorail does not review contracted inspectors’ credentials or qualifications thoroughly enough.

In all, how Metro currently handles structural inspections creates “the risk that safety issues could be misidentified or slip through the cracks.”

Another issue is that Metrorail has yet to provide load ratings for its elevated structures, meaning it’s unclear the size and weight limit of trains and equipment that can safely traverse a bridge or station. This creates a risk that the structures “could be inadvertently overloaded,” according to the audit.

The audit makes the conclusion that all of these issues “demonstrates a separate significant, ongoing problem facing Metrorail: siloed departments that do not fully coordinate on work instructions, materials or procedures.”

All aspects of Metro are audited over a three-year cycle, but the structural inspection process was audited now “due to other othersight work that identified concerns,” a WMSC spokesperson tells Reston Now.

Metrorail has 45 days to submit corrective action plans for the issues to the safety commission.

Beyond that, the timeline isn’t clear of when these required changes will actually take place.

The WMSC spokesperson also tells Reston Now that while some of these items are “relatively straight forward” others, like proper training, could take more time.

When reached for comment, a Metro spokesperson wrote Reston Now via email that they are addressing the issues:

Metro appreciates the efforts of the WMSC in completing this audit, especially the acknowledgement of the substantial progress that Metro has made with our structural assessment and maintenance programs. We require inspection of bridges and related structures at least every two years, more frequently in some instances, to ensure structural integrity and the safety of the riding public.

In addition to inspection and maintenance programs, Metro is investing in an aggressive capital program to ensure the state of good repair of our elevated structures, including addressing priority projects. As we review the findings of this audit and develop our responses, we remain committed to continuous improvement of our program and enhancing the safety of the system.

All of this has left the status and timeline of Silver Line Phase 2, which includes the opening of Reston Town Center Station, Herndon Station, and four other stations extending into Northern Virginia, up in the air.

Over the last several months, a number of audits and reports have called out Metro and have threatened to delay the openings.

In the fall, a WMSC audit reported that Metro’s Rail Operations Control Center is a “toxic workplace” with “racial and sexual comments, harassment, and other unprofessional behavior.”

In September, a report from the Metro’s Office of Inspector General found 342 cracks in concrete panels at a number of Silver Lane Phase 2 stations. This was due to the use of faulty materials, read the report.

As of last month, Phase 2 could still open by the fall this year, but that’s at the earliest.

Reston Now followed up with the Metro spokesperson about an updated timeline for the opening of Silver Line Phase 2, but has yet to receive an answer as of publication.

Photo courtesy of Metropolitan Washington Airports Authority

Recent Stories

The Fairfax County Board of Supervisors faces tough decisions ahead of next week’s budget markup session, following demands from local unions to increase county employees’ wages.Last week, dozens of county…

Reston’s popular community yard sale is temporarily moving down the road. More than 3,000 people are expected to attend the biannual event when it returns this Saturday (April 27), according to Reston Association, the organizer.

Morning Notes

Virginia bluebells bloom in Reston (photo by Marjorie Copson) Clifton Family Mourns Sons Killed in Fire — “When Fairfax County firefighters found two boys inside a fiery Virginia house earlier…

Marc Smith will serve as the new Herndon economic development director starting in May (courtesy Town of Herndon) The Town of Herndon is getting a new director of economic development….

×

Subscribe to our mailing list