Expanded Route 7 Set for July 2024 Completion

Nosie Barrier being installed along Route 7, between Reston Avenue and Utterback Store Road (Photo courtesy of VDOT)

(Update 3/3) A major project to widen nearly seven miles of Route 7 between Reston Avenue and Jarrett Valley Drive remains on track for completion by July 31, 2024.

It is also expected to be completed within its $314 million budget, confirms Jennifer McCord, a  Virginia Department of Transportation spokeswoman.

The improvements include widening the heavily-trafficked road – also known as Leesburg Pike – from four to six lanes, adding shared-use paths for pedestrians and bikers, and making major design changes to intersections.

It’s all being done within the guidelines of the Fairfax County Comprehensive Plan.

The project was first discussed nearly a decade ago, approved in 2017 with construction beginning two years ago, in the spring of 2019. It’s expected to take just over five years to complete.

Over the last two months, construction has continued at different sections of the road.

Between Reston Avenue and Utterback Store Road, a noise barrier is currently being added as well as the installation of a storm sewer between Reston Avenue and Baron Cameron Avenue.

From Baron Cameron Avenue to Colvin Run Road, existing asphalt was removed.

In the Difficult Run Area, work has continued on the new Colvin Run as well as excavation for the pedestrian tunnel that will run under Route 7.

Between Faulkner Drive to Jarrett Valley Drive, water main relocations and traffic shifts are taking place.

Landscaping work and third-party utility relocations are underway throughout the roadway.

This construction has also resulted in a number of traffic changes and lane closures that are constantly shifting.

In the upcoming months, crews will begin removing the Route 7 bridge over Difficult Run and will eventually complete a higher, longer bridge to replace it.

Colvin Run will also be diverted to a new stream channel. Small weirs (barriers) are being placed in the stream bed to encourage a meandering flow pattern and vegetation growth.

Construction will also continue on the pedestrian tunnel underneath Route 7 connecting the north and south sections of Colvin Run Mill Park.

Despite the ongoing work, public access to the Gerry Connolly Cross County Trail will be maintained.

While crews continue to work with COVID-19 safety protocols in effect, the decreased traffic volume in the earlier part of the pandemic has allowed VDOT to extend work hours in certain cases.

Photo courtesy of VDOT

Recent Stories

Morning Notes

Beaver munching on grass by Walney Pond in Chantilly (staff photo by Angela Woolsey) Shake Shack proposed for Kamp Washington Shopping Center — “Fairfax City Board of Architectural Review approved…

Taim Mediterranean Kitchen is officially open in Reston (Photo courtesy taim). Taim Mediterranean Kitchen in Reston has permanently closed just four months after its opening. The New York-based chain, known…

Morning Notes

Cat (staff photo by Vernon Miles) Cat declawing to be banned in Virginia — “Veterinarians will not be allowed to declaw cats in Virginia starting in July, unless there are certain…

The Knutson Companies is thrilled to announce new opportunities for Loudoun County living with the release of a new section of rooftop terrace townhomes and a brand new community of…

×

Subscribe to our mailing list