Lake Thoreau pool renovations hit more roadblocks due to contractor availability and material costs

The $3.5 million renovation of Reston Association’s Lake Thoreau pool has hit more roadblocks, this time due to lack of contractor availability and soaring material costs.

Already three months behind initial estimates, an October groundbreaking remains the official goal, but there’s a likelihood that the date will be pushed back again.

“Due to the volatility of the construction market, narrowing down the final estimate for this project is challenging,” RA spokesperson Mike Leone told Reston Now in an email. “Assuming the timeline holds, construction would start around October but there is a possibility it could be pushed into November.”

RA recently sent out requests to 10 contractors for pre-qualifying bids on the project, but the association received only two responses.

“This is a little bit disappointing, but indicative of the market that many, many contractors are very, very busy,” Chief Operating Officer Larry Butler said at RA’s Board of Directors meeting last Thursday (May 27).

Butler said the hope is to bring on a contractor when the project design and development are 80% complete, so the contractor can provide their own insight and expertise before sending it to Fairfax County for approval.

Leone says it’s expected that a contract with a general contractor will be ready for review and approval by the RA board in August or September.

Another element currently complicating the project is fast-rising material costs. Butler notes that the $3.5 million project budget was established prior to the recent spike in material costs.

“Here’s a really crazy example…There’s a lot of piping in pools. PVC costs are up 270% from March 2020 to March 2021,” Butler explained.

The hope is that prices will stabilize and drop, but “it’s an ever-moving target,” he says.

The overall cost of the renovations and the means of paying for them have been an ongoing source of conflict since the project first started in late 2019. The project is now rather lean, though at least one RA board member was asking about the potential for further cuts.

The issues with the Lake Thoreau renovations come as RA contemplates raising member assessments and, possibly, repurposing other pools  due to ongoing budgetary challenges.

Key design elements being added or modified at Lake Thoreau pool include ADA access to the main pool, re-working of the roof geometry, a zero-depth area, a repositioning of the spa away from the bathhouses, and a redesign of the overlook deck. A pollinator garden will also be added near the parking lot.

The renovations are expected to be completed about a year after construction begins, so that could be in October or November 2022. A grand reopening of Lake Thoreau pool is anticipated in May 2023.

However, Leone cautions that the timing could change.

“If the start of construction is delayed for whatever reason, then there is a chance the grand re-opening could be delayed,” he told Reston Now.

Photo via Reston Association

Recent Stories

Morning Notes

Beaver munching on grass by Walney Pond in Chantilly (staff photo by Angela Woolsey) Shake Shack proposed for Kamp Washington Shopping Center — “Fairfax City Board of Architectural Review approved…

Taim Mediterranean Kitchen is officially open in Reston (Photo courtesy taim). Taim Mediterranean Kitchen in Reston has permanently closed just four months after its opening. The New York-based chain, known…

Morning Notes

Cat (staff photo by Vernon Miles) Cat declawing to be banned in Virginia — “Veterinarians will not be allowed to declaw cats in Virginia starting in July, unless there are certain…

The Knutson Companies is thrilled to announce new opportunities for Loudoun County living with the release of a new section of rooftop terrace townhomes and a brand new community of…

×

Subscribe to our mailing list