As School Year Begins, First Phase of Herndon High School Renovation is Nearly Complete

Students who poured through the halls of Herndon High School on the first day of school yesterday were the first to take advantage of the school’s newest renovation features.

So far, phase one of the major renovation project is nearly complete. Improvements include a new entrance that requires entrances to pass through security and the main office, 65 classrooms, a new gourmet foods room, new science labs and additional classroom spaces.

The new library, which is part of phase one, is behind construction and is expected to open in the coming weeks. For now, students will use the old library, but services will be limited.

Phase two will include new locker rooms, art rooms, an expanded main gym, and a renovated auxiliary gym. Phase three will include a new wrestling and gymnastic rooms, renovated musics rooms and an auditorium, and upgraded baseball and softball structures. The final phase will feature updates to the cafeteria, a new food court design, and updates to the tennis courts and stadium press box.

More than 60 outdoor trailers are expected to remain until next year. School officials said only one trailer was removed over the summer in order to allow construction to take place. Because trailers are in place, a parking lottery will continue, with seniors given priority. The school is working with Herndon United Methodist Church to expand student parking opportunities.

The school’s special education office is now in the new wing of the building. A temporary boys locker room and school clinic is also in place as construction continues.

Photos via Herndon High School

Recent Stories

The skeletal remains of Michael Delaney, the Reston man who went missing from Reston Hospital in May 2020, have been found in the Sugarland Run area, Fairfax County police confirmed….

One of the two residential towers planned for the Faraday Park development near the Wiehle-Reston East Metro station is now open to residents. Move-ins for 242-unit Faraday West tower officially…

Open houses this weekend include a 4 BD/2.5 BA home on a large lot with a swimming pool.

Reston Community Center has announced the lineup its 2021-22 Professional Touring Artist Series. After a truncated season with limited audiences last year due to the COVID-19 pandemic, the series will…

×

Subscribe to our mailing list