Restoration of Sugarland Run Stream Remains in Design Phase, Says Town of Herndon

Updated on Feb. 1 to correct information on the project phase and jurisdiction receiving funding

Despite being approved more than two years ago, the construction phase of the restoration of Sugarland Run (South) Stream still hasn’t begun.

The $1.2 million project remains in the design phase, according to the Town of Herndon’s deputy Director of Public Works John Irish, though it’s expected to be completed by May.

The project will improve stormwater systems, stabilize erosion along streambanks, prevent flooding, and ensure the stream meets requirements for Chesapeake Bay Total Maximum Daily Load, first established in 2010. It will do this by planting vegetation, in-stream structure placement, and installing brush mattress.

The conditions along the stream banks and stream valley have been deteriorating in recent years.

The project will also restore a portion of the stream that flows near the Washington & Old Dominion Trail crossing.

The town received $200,000 from Fairfax County for the design work, which includes the geomorphic assessment, surveying, and public outreach meetings.

Irish writes to Reston Now in an email that this phase is “approximately 95% completed.”

In all, the design phase will end up taking up nearly three years. This is due to Herndon being asked by the county to apply for and, then, waiting for a state grant.

A stream condition assessment and negotiation of a fee that met budgetary guidelines also took time, writes Irish.

All in all, design work didn’t start until February 2020.

After designs are completed in May, they will be sent to the county with a request for one million dollars for construction. Once those funds are received, Herndon will advertise for construction bids.

Despite seemingly a long way to go in the process, Irish says construction is still expected to start this summer and completed within six months of the awarded contractor being given the go-ahead.

That means the project could be completed by the end of 2021 or early 2022.

The initial funding agreement did estimate the project could take up to four years, so the project theoretically could still be completed on time if not early.

However, a spokesperson for Fairfax County Department of Public Works and Environmental Services tells Reston Now that this particular project is “lower priority” as part of their full Sugarland Run Watershed Management Plan, which was first adopted in 2010.

It remains unclear how this assessment will impact the expected providing of one million dollars to the Town of Herndon for construction and completion of Sugarland Run Stream restoration later this year.

Recent Stories

Marc Smith will serve as the new Herndon economic development director starting in May (courtesy Town of Herndon) The Town of Herndon is getting a new director of economic development….

Morning Notes

Reston (staff photo by Scott Brodbeck) Demolition begins at burned hust of Oud Resto and Hall — “The site of the Main Street restaurant that burned down in 2020 is where…

OmBaked CBD Boutique at Lake Anne Plaza in Reston (staff photo by James Jarvis) OmBaked CBD Boutique at Lake Anne Plaza in Reston is hosting a holistic health fair next…

Morning Notes

Boaters and geese can be seen in the distance on Lake Accotink (staff photo by Angela Woolsey) Man fires gun at dog, Fairfax County police say — “Fairfax County Police…

×

Subscribe to our mailing list