The Reston Community Center has once again delayed the opening date of its renovated Terry L. Smith Aquatics Center. The facility is expected to open in January, two months later than originally estimated.
Delays were caused by challenging completing interlocking activities, according to RCC. For example, work on plumbing, electrical and mechanical pumping systems is dependent on each other. Additionally, tiling must be done while the deck space is used to access other work areas.
In a statement posted online, RCC stated that Branch Builds, the contractor, expects the project to be completed by Jan. 3.
“Branch Builds is working with its sub-contractors to schedule as much work simultaneously as feasible, but this sequential nature of the work makes that challenging. As much weekend, overtime and extra work as possible is being scheduled to move forward expeditiously,”
Here’s more from the statement:
|
As a result, activities planned before Jan. 4 will be canceled and the start of Saturday and Sunday swim lessons will begin on Jan. 11. Learn-to-swim and exercise programming will remain on schedule, with a start date of Jan. 6.
RCC says it will monitor progress daily to determine if other action is needed.
The facility — which was built in 1979 — was closed this year to jumpstart the renovation effort.