A connection has now been solidified between Herndon Metro station and Van Buren Street.
The Town of Herndon has completed construction of an 800-foot trail for pedestrians and bicyclists that connects the Metro station to Van Buren Street by Worldgate Centre.
“The 800-foot trail provides ready access to Metro for workers in the Worldgate and nearby office complexes,” the Town of Herndon said.
The trail goes live as Bike to Work Day kicks off on Friday (May 19). The Herndon area will have pit stops at the Innovation Center Metro station and the Town Hall Green.
Construction on the project began in September 2022. The project was completed roughly two months ahead of schedule, according to town spokesperson Anne Curtis.
The overall project cost $600,000 for design and construction. It was funded through a combination of town funds as well as funds from Fairfax County’s Herndon Metrorail Station Access Management Study.
The trail was officially opened last week, not long after construction finished on nearby improvements along Van Buren Street from Spring Street to Herndon Parkway. That “complete streets” project widened the road, added curb-and-gutter and bicycle lanes, and made some intersection and stormwater upgrades.