Silver Line Phase 2 Opening Delayed 13 Months

First Silver Line train pulls in to Wiehle-Reston East/Credit: Mike Heffner, Vita Images The Metropolitan Washington Airports Authority said on Monday that design modifications for safety and reliability of Metro’s Silver Line will delay the opening of Phase 2 for about 13 months.

Phase 2, which will run from Wiehle-Reston East to Dulles International Airport and into Loudoun County, was most recently projected to open in late 2018. This means it might not open until late 2019.

MWAA constructed Phase 1 of the Silver Line, which opened in July 2014 (about six months behind schedule). Phase 1 has five stops from Tysons Corner to Reston. It is also building Phase 2, which is projected to cost $2.7 billion and will expand the line from Wiehle-Reston East to Reston Town Center, Herndon, Route 28, Dulles International Airport and Ashburn.

More than 150 modifications have been made and integrated into the design for Phase 2, says MWAA. Many of these modifications parallel design changes made in the latter stages of Phase 1 and will enhance the safety and reliability of Phase 2.  The modifications, when combined with associated weather and construction delays, have extended the Phase 2 construction schedule by about 13 months, MWAA officials said.

“Over 100 design changes were made in Phase 1 — a large number of them ordered in the final months of the construction process — requiring additional design, engineering, construction, management and oversight work,” Charles Stark, the Airports Authority’s executive director of the Silver Line project, said in a statement.

“For consistency, many of these same safety and reliability modifications needed to be incorporated into Phase 2 of the project, which then impacted the schedule.”

MWAA announced late last year that the entire 11-mile Phase 2 would need changes to comply with new stormwater regulations.

Meanwhile, MWAA said remaining work done to finalize Phase 1 of the project will add $76 million, or about 2.6 percent, to the previously announced Phase 1 cost of $2.8 billion.

The new Phase 1 cost of $2.982 billion remains within the original federally approved Phase 1 budget and toll rates on the Dulles Toll Road will not be affected, MWAA said. Toll rates will remain at current levels through 2018.

From MWAA:

A recently concluded global settlement with the construction contractor for Phase 1, Dulles Transit Partners, along with the resolution of other outstanding matters – including the close-out of Virginia permits which allowed Phase 1 work within Routes 7 and 123 in Tysons Corner, and the execution of contracts to supplement certain Phase 1 work, as required by WMATA – has allowed the Airports Authority to project a final Phase 1 close-out cost of $2.982 billion, which represents an additional cost of about $76 million, and to move to the final close-out of the Phase 1 project.

The majority of the remaining work on Phase 1, which opened for business in July 2014, will be completed by the end of this year, including the delivery of 64 new rail cars at a cost of $189.4 million to expand the Metrorail fleet.  Final close-out of Phase 1 is expected to occur in 2016.

“The Phase 1 global settlement is an important milestone in the Silver Line project, following its successful launch in July 2014,” Airports Authority CEO Jack Potter said.  “It gives us closure on the most substantial cost component of Phase 1, ensures we will achieve the project’s federal budget targets and allows us to maintain the existing toll schedule for the Dulles Toll Road.”

The ultimate impact of the Phase 1 additional costs may be reduced or even eliminated if the contingency budget for Phase 2 of the Silver Line project is not fully used and the total project, both Phases 1 and 2, comes in at or under the overall project budget.

The Airports Authority also announced an update to the construction schedule for Phase 2 of the Silver Line project, which will extend service from the terminus of Phase 1 in Reston, Virginia, through Washington Dulles International Airport and into Loudoun County, Virginia.

Potter said, “The added costs arising from Phase 2 design modifications will remain within the Phase 2 contingency budget of $550 million and will have no effect on the toll rates on the Dulles Toll Road. With our project partners, we are committed to limiting future design changes. Phase 1 is already experiencing ridership beyond expectations, and significant construction and development is underway along its path in the Dulles Corridor. We are confident that Phase 2 will experience similar success.”

Recent Stories

Morning Notes

A man walks a dog into McLean Central Park (staff photo by Angela Woolsey) Special Education Disparities Persist in FCPS — “Students with disabilities in Fairfax County Public Schools perform…

The Herndon Metro station (staff photo by Jay Westcott) With the Silver Line Phase II opening still in flux, Fairfax County is being asked to pay another $40 million. At…

Route 7 has a new eastbound lane between Reston Avenue and Riva Ridge Drive (via VDOT) Drivers headed east on Route 7 in Reston can now get a small taste…

Morning Notes

Fairfax County Fire and Rescue responded to a burned-up elevator motor at 226 Maple Avenue in Vienna on Saturday (staff photo by Angela Woolsey) Metro Extends Blue Line Shutdown —…

The Ravel Dance Studio will re-open for fall classes 2020. The school will offer in person and virtual online instruction. With over 5000 sq. ft. to social distance the school has added air ionization filtration systems, ballet barres, acrylic dividers, hands free bathrooms, strict monitoring and more.

The Ravel Dance Studio will produce a Nutcracker Ballet Hollywood style video through the Reston Community CenterStage. REGISTRATION online begins August 17.

Submit your own Community Post here for just $99.

Chris Green is one of the DMV’s finest fitness instructors. A Lululemon and South Block ambassador, he is a coach and mentor to so many. He embodies grace, positivity and motivation in ways that no one else can. If we could all learn a thing or two from him, the world would be a much better place. He does so much for others, and does so with a smile on his face 99% of the time.

He recently ruptured his Achilles and has an incredibly long and tough journey ahead. As if COVID hadn’t impacted fitness professionals enough, throw this in the mix and it’s a double, even triple whammy. CG is no longer able to work and do what he loves for the time being because of this and we’d love your support.

Read More

Submit your own Community Post here for just $99.

×

Subscribe to our mailing list