Reston Parkway Part of VDOT Bridge Repairs in 2016

Bridge Over Dulles Toll Road/Credit: VDOT

Repairs to Reston Parkway’s bridge over the Dulles Toll Road will be part of a Virginia Department of Transportation’s (VDOT) $5.6 million project next spring.

VDOT says it will be performing preventative maintenance projects on bridges on Monroe Street, the Herndon-Monroe Park and Ride Ramp and Reston Parkway in advance of Metro’s Silver Line Phase 2, which is currently under construction.

The main purpose of the project is eliminating and closing the bridge deck joints above the Silver Line tracks. Doing it before Phase 2 opens in 2019 will save VDOT money in the end, the department says.

“Future construction of the tracks in the median of Route 267 (the Dulles Toll Road) will limit the access to the bridge existing piers,” VDOT said in a statement. “The cost of performing any future repairs to the bridge piers would need to include cost of coordination with Metro, which would significantly increase future repair costs.”

The Reston Parkway dual bridges over the Toll Road are 385-foot.-long, six-simple- span, steel plate girder bridges.

The northbound bridge was constructed in 1959 and widened and deck-replaced in 1989. The northbound total bridge width is 42.33 feet and consists of a 1.66-foot raised median, one-foot shoulder, three 12-foot traffic lanes, two-foot shoulder and 1.66-foot barrier.

The southbound bridge was constructed in 1976 and widened in 1989. The southbound total bridge width is 51.66 feet and consists of a 1.66-foot raised median, one-foot shoulder, three 12-foot.traffic lanes, three-foot shoulder, 1.66-ft. barrier, 8.33-foot. path and one-foot curb with pedestrian fence.

The Monroe Street/Van Buren Street dual bridges over the Toll Road are 378-foot-long, six-single-span, steel plate girder bridges. There is a 38-foot gap between the northbound and southbound bridges. The northbound bridge was constructed in 1963, and the deck was milled and overlaid in 1989. The southbound bridge was constructed in 1989.

The Herndon-Monroe Park and Ride Ramp bridge is a 613-foot-long, seven-single-span, steel plate girder bridge. The bridge was constructed in 1999.

Here is more cost and scheduling info:

Monroe Street/Van Buren Street Bridge Joint Closures
Anticipated Schedule
Advertisement for construction – March 2016
Construction – May 2016

Estimated Costs
Preliminary engineering – $180,000
Construction – $530,000
Total – $710,000

Herndon-Monroe Park and Ride Ramp Bridge Joint Closures
Anticipated Schedule
Advertisement for construction – March 2016
Construction – May 2016

Estimated Costs
Preliminary engineering – $168,000
Construction – $500,000
Total – $668,000

Reston Parkway Bridges Deck Mill and Overlay and Barrier Repair
Anticipated Schedule
Advertisement for construction – March 2016
Construction – May 2016

Estimated Costs
Preliminary engineering – $132,000
Construction – $1.4 million
Total – $1.5 million

Reston Parkway Bridge Joint Closures
Anticipated Schedule
Advertisement for construction – March 2016
Construction – May 2016

Estimated Costs
Preliminary engineering – $200,000
Construction – $2.5 million
Total – $2.7 million

Photo: Bridge over Dulles Toll Road/Credit: VDOT

Recent Stories

Herndon has finalized its vision for mixed-use development in the Transit-Related Growth Area (via Town of Herndon) In the future, Herndon hopes to see a vast swath of land near…

The Fairfax County Board of Supervisors (staff photo by James Jarvis) The Fairfax County Board of Supervisors has signed off on a 3-cent bump in its real estate tax rate,…

New vehicle lanes and a shared-use trail are officially open to travelers on Route 7 (Leesburg Pike) after almost five years of construction. The Virginia Department of Transportation announced last night…

Morning Notes

Buildings are under construction near the Wiehle-Reston Metro station (staff photo by Angela Woolsey) Man Gets Life in Prison for N. Va. Gang Killings — An MS-13 leader was sentenced…

×

Subscribe to our mailing list