Photos: RCC’s Aquatics Center Nears Halfway Point for Renovation

The Reston Community Center is now in its fourth month of a nine-month renovation of the Terry L. Smith Aquatics Center.

Demolition of the existing pool and surrounding deck, which started in late January, finished in March, according to an update from RCC. The demolition resulted in more than eight tons of steel from the ductwork and ceiling that will get recycled. Several tons of concrete, rebar, stainless steel drains and other materials were salvaged.

“In addition, the excavation revealed that the years-long water infiltration problems RCC experienced probably resulted from a combination of poor drainage and water leaking from the pool shell,” the April 1 update said, adding that the project will include corrective measures for the drainage issues and ensure the new pools have water impermeable shells.

The 40-year-old aquatics center is getting a makeover that will add two pools — a 25-yard lap pool with zero-depth entry and a warm-water therapeutic pool — along with a new roof. The facility is slated to reopen in October.

Photos via Reston Community Center

Recent Stories

Reston Association (staff photo by Jay Westcott) Reston Association is seeking candidates for its 2024 Board of Directors’ election. Four seats are open for the election, which will take place…

Live Fairfax is a bi-weekly column exploring Fairfax County. This recurring column is sponsored and written by Sharmane Medaris of McEnearney Associates. Questions? Reach Sharmane at 813-504-4479. Embarking on the holiday season demands…

Gov. Glenn Youngkin announces a “Building Blocks for Virginia Families” plan to increase funding for early childhood education (Official Photo by Christian Martinez, Office of Governor Glenn Youngkin) With the…

A renovation of Lake Thoreau pool has been completed (courtesy Reston Association/YouTube) The renovation of Reston’s Lake Thoreau pool has officially been completed in time for the 2024 pool season….

×

Subscribe to our mailing list