Metro Pushes Silver Line Expansion Deadline to September

The new silver line metro expansion is expected to be completed around September — instead of its July 2020 goal.

Testing is already underway for the new trains, and Fairfax County reported earlier this month that the project is about 97% complete, but several structural issues hinder project completion, according to WTOP.

The concerns revolve around cracks in concrete outside the station, deterioration of panels framing the station and uneven tracks where trains cross one another, WTOP reported in November.

“The Metropolitan Washington Airports Authority and its contractors who are building the rail line are confident the concrete panel issues have been addressed with protective sealant, which will be reapplied approximately once every 10 years,” according to WTOP.

Now, final construction continues around Reston and Herndon.

The Innovation Center Station garage is 92% complete, $5 million under budget and is expected to be completed in February, according to Fairfax County’s Department of Transportation (FCDOT).

For the Innovation Center Station itself, FCDOT staff told the Board of Supervisors earlier this week that crews were working on fixing communication systems and placing art in the north pavilion.

At the Reston Town Center Station, crews were installing speakers in the ceiling and working on stormwater management.

Photo via Fairfax County

Recent Stories

An encampment has taken shape in recent years near the Sunrise Assisted Living in Reston (staff photo by Fatimah Waseem) A tent encampment housing between 20 and 35 individuals in…

Fairfax County Courthouse (staff photo by James Jarvis) The Fairfax County Board of Supervisors is considering using kiosks equipped with artificial intelligence to provide select legal information in a variety…

Just a day after negotiations for a Washington Wizards and Capitals arena in Alexandria officially fell through, George Mason University has announced that it’s no longer planning to build a joint baseball and cricket stadium in Fairfax for the Washington Freedom.

Fox Mill Road in Herndon will be closed on April 1 (via VDOT) Fox Mill Road will be closed at the beginning of next month to allow for a pipe…

×

Subscribe to our mailing list