As construction gears up for widening Route 7 from Reston to Tysons, “Pardon Our Dust” meetings starting later this spring with information on the upcoming work phases and schedules.
The proposed Virginia Department of Transportation (VDOT) project will transform nearly seven miles of Route 7, between Reston Avenue and Jarrett Valley Drive, which is just before the Dulles Toll Road interchange.
The project will widen Route 7 from four to six lanes, add shared-use paths and revamp intersections along the corridor.
The project aims to “increase capacity, improve safety and traffic flow and enhance mobility for cyclists and pedestrians, all in conformity with Fairfax County’s Comprehensive Plan,” according to VDOT.
Washington Gas has been busy with work along the corridor to replace a little under 7 miles of pipeline along Route 7 from Bishop Gates Way in Herndon to the intersection of Baron Cameron Avenue and Springvale Road.
The schedule for the project on VDOT’s website says:
- late summer 2018-summer 2020: final design
- early 2019-early 2021: right of way
- spring 2019-summer 2023: utility relocation
- spring 2019-summer 2024: construction
The project is slated to finish in July of 2024, VDOT says.
Specific dates and locations for the “Pardon Our Dust” meetings, which will periodically occur from this spring through summer 2023, have not been announced yet.