Environmental Approval Still Pending for $170 Million Soapstone Connector Project

State and local transportation officials have been working for more than a year on clearing the Soapstone Connector through the environmental approval phase — one of the latest hurdles for the roughly $170 million project.

The connector — which extends Soapstone Drive from Sunrise Valley Drive over the Dulles Toll Road to Sunset Hills Road — provides a new north-south alternative to tackle increasing traffic congestion on Wiehle Avenue. By the time the project breaks ground, hundreds of additional residential units are expected to come on the market in Reston.

County transportation officials are working with the Virginia Department of Historic Resources to determine the next steps for the project after the state determined a group of buildings on Association Drive the project could cut through are considered historic. The Fairfax County Department of Transportation must conduct an alternatives analysis to find possible ways to reduce the impact on the buildings.

Discussions have been ongoing for more than year. The county’s Architectural Review Board first determined the collection of buildings could be historically significant in early 2018. Since then, county staff have been trying to chart the best path forward to minimize the impact on the buildings  — which are considered historic as a collection, but not on an individual basis.

More hurdles are expected as the project goes through design and planning. Construction isn’t expected to begin until the mid to late 2020s.

“Anytime you’re building a new major project in a built environment, it’s more challenging than if we’re working out in a cornfield,” Tom Biesiadny, FCDOT’s director, told Reston Now. “None of them are insurmountable.”

Although funding for the project has not been secured yet, Biesiadny says the county has enough dollars to finish project design, which will move forward once the county receives necessary environmental approvals. The county plans to then tackle right-of-way and land acquisition between 2022 and 2024. Utility relocation is also complicated by the fact that area businesses rely on fiber optic cables along Sunrise Valley Drive and Sunset Hills Road.

“At the moment, money is not holding anything up,” Biesiadny said. “It’s several years out before we need the construction dollars.”

So far, the project has $24 million secured from federal, regional and local funds. A $45.4 million grand application for Smart Scale funding has been submitted. The county plans to continue to aggressively apply for grant funding.

The connector has been on the county’s planning books for years. A hybrid design for the project received county approval in 2014.

Map via Fairfax County Government

Recent Stories

An encampment has taken shape in recent years near the Sunrise Assisted Living in Reston (staff photo by Fatimah Waseem) A tent encampment housing between 20 and 35 individuals in…

Fairfax County Courthouse (staff photo by James Jarvis) The Fairfax County Board of Supervisors is considering using kiosks equipped with artificial intelligence to provide select legal information in a variety…

George Mason University has been exploring plans to expand its West Campus off of Braddock Road (staff photo by Angela Woolsey) It has not been a great week for plans…

Fox Mill Road in Herndon will be closed on April 1 (via VDOT) Fox Mill Road will be closed at the beginning of next month to allow for a pipe…

×

Subscribe to our mailing list