Innovation Center Station Garage Nearly Complete as Silver Line Expansion Date Nears

The garage at Innovation Center Metro Station is nearly complete.

The $52 million project is almost entirely built-out. Crews must now install elevators, finish installing utilities and complete the final concrete work outside the garage.

Metro officials said the project required $5 million less than what was originally allocated.

Construction on the 11-mile extension of the Silver Line is also nearly complete, but concerns about deficiencies in the concrete panels and concrete ties have stalled the project.

Currently, site inspections and safety testing are ongoing. Previously approved shutdowns for the Wiehle-Reston East Station on weekends were canceled due to pending system integration work.

Metro does not plan to accept the rail project the Metropolitan Washington Airports Authority until both the rail yard and mainline tracks are complete. The start of service is expected to begin by October this year.

Photos via handout/Fairfax County Government

Recent Stories

Before we head into a weekend, let’s take a look back at the biggest stories on the site in recent days. Pet of the Week: Bear who, after living outside…

Construction on a new pedestrian bridge over Wiehle Avenue is set to begin sometime next summer. The bridge, which would connect to the Washington & Old Dominion Trail, is intended…

Zoomph, a Reston-based tech company that started in 2016 is continuing to build national partnerships. Its digital platform provides social media post metrics for sports clients along with detailed demographic…

For anyone who feels strongly about whether or not Lee Highway and Lee-Jackson Memorial Highway should continue to bear those names, the time to share that opinion has arrived. The…

×

Subscribe to our mailing list