Thursday Morning Notes

Tower Crane To Be Removed Next Weekend — Crews will remove a tower crane from the median of the Dulles International Airport Access Highway between the Fairfax County Parkway overpass and the Reston Parkway overpass, June 2-5. The crane has been working on the future Reston Town Center Metro station. [Dulles Corridor Metrorail Project]

VideoBlocks Moving to Arlington — After announcing last year that the company would be moving from Reston to Arlington, subscription stock video service VideoBlocks has settled on a location. [Washington Business Journal]

Fairfax 275 Committee To Meet Here — The 275th Commemoration Steering Committee will meet at Lake Anne Brew House on June 1, celebrating the county’s official anniversary month and gearing up for the Historically Fairfax: 275th Celebration Fair, June 17. [Facebook]

Church Celebrating Centenarian’s Birthday — Virginia M. Calloway, the oldest member of the Heritage Fellowship Church on Fox Mill Road, will turn 104 on June 4. [Reston Connection]

0 Comments

Friday Morning Notes

Reston-Based Software Company Looking to Grow — Oracle is seeking new talent in the effort to outpace the competition in fields such as artificial intelligence and virtual reality. [Fairfax County EDA]

Crane Removal to Affect Toll Road Traffic — Eastbound traffic on the Dulles International Airport Access Highway will be detoured onto the Toll Road tonight through Monday morning as the tower crane at the future Herndon Metro station is disassembled and removed. [Dulles Corridor Metrorail Project]

Town of Herndon Adopts $51M Budget — The budget, approved this week by the Herndon Town Council, features no tax rate increases. It also includes resources to support development of a first-class arts facility to act as an economic driver for the downtown. [Town of Herndon]

Civil War Stories at Frying Pan Park — The Meeting House at Frying Pan Farm Park (2739 West Ox Road, Herndon) served as a field hospital, encampment and picket post during the Civil War. From 1-3 p.m. Sunday, re-enactors, exhibits and a special guest speaker will share information about the lives of those soldiers. [Fairfax County Park Authority]

0 Comments

Silver Line construction/Photo by Jennifer Thomas Alcott, Capital Rail Constructors

Phase 2 of construction on Metro’s Silver Line is more than 56 percent complete, according to information released today by the Dulles Corridor Metrorail Project.

The Metropolitan Washington Airports Authority is overseeing construction of the 11.4-mile Phase 2 extension of the Silver Line from Reston through Dulles Airport to Ashburn. Engineering and design work on the phase began in July 2013, and the project is expected to be complete by 2020. All told, the stretch will include six rail stations; nine entrance pavilions and pedestrian bridges; aerial guideways through Dulles Airport; and 89,000 feet of track.

Silver Line construction/Capital Rail Constructors“Bad weather never really stopped us,” project vice president Charles Stark is quoted as saying regarding construction efforts in recent months.

Station wall work is currently underway at the future Reston Town Center station, while structural steel installation for the vault roof has begun at the future Herndon station, also located in Reston. In addition, piers for pedestrian bridges are being put up. All needed pier caps have been poured, along with 76 percent of deck spans. Construction on the rail yard at Dulles Airport is 46 percent complete, according to project officials.

Work also began in December on a new Herndon Metro parking garage, a county project.

Phase 2 of the Silver Line was originally projected to be completed by late 2018; however, design modifications later pushed that date back.

Photos courtesy Capital Rail Constructors/Dulles Corridor Metrorail Project