Lake Thoreau pool renovations hit more roadblocks due to contractor availability and material costs

The $3.5 million renovation of Reston Association’s Lake Thoreau pool has hit more roadblocks, this time due to lack of contractor availability and soaring material costs.

Already three months behind initial estimates, an October groundbreaking remains the official goal, but there’s a likelihood that the date will be pushed back again.

“Due to the volatility of the construction market, narrowing down the final estimate for this project is challenging,” RA spokesperson Mike Leone told Reston Now in an email. “Assuming the timeline holds, construction would start around October but there is a possibility it could be pushed into November.”

RA recently sent out requests to 10 contractors for pre-qualifying bids on the project, but the association received only two responses.

“This is a little bit disappointing, but indicative of the market that many, many contractors are very, very busy,” Chief Operating Officer Larry Butler said at RA’s Board of Directors meeting last Thursday (May 27).

Butler said the hope is to bring on a contractor when the project design and development are 80% complete, so the contractor can provide their own insight and expertise before sending it to Fairfax County for approval.

Leone says it’s expected that a contract with a general contractor will be ready for review and approval by the RA board in August or September.

Another element currently complicating the project is fast-rising material costs. Butler notes that the $3.5 million project budget was established prior to the recent spike in material costs.

“Here’s a really crazy example…There’s a lot of piping in pools. PVC costs are up 270% from March 2020 to March 2021,” Butler explained.

The hope is that prices will stabilize and drop, but “it’s an ever-moving target,” he says.

The overall cost of the renovations and the means of paying for them have been an ongoing source of conflict since the project first started in late 2019. The project is now rather lean, though at least one RA board member was asking about the potential for further cuts.

The issues with the Lake Thoreau renovations come as RA contemplates raising member assessments and, possibly, repurposing other pools  due to ongoing budgetary challenges.

Key design elements being added or modified at Lake Thoreau pool include ADA access to the main pool, re-working of the roof geometry, a zero-depth area, a repositioning of the spa away from the bathhouses, and a redesign of the overlook deck. A pollinator garden will also be added near the parking lot.

The renovations are expected to be completed about a year after construction begins, so that could be in October or November 2022. A grand reopening of Lake Thoreau pool is anticipated in May 2023.

However, Leone cautions that the timing could change.

“If the start of construction is delayed for whatever reason, then there is a chance the grand re-opening could be delayed,” he told Reston Now.

Photo via Reston Association

Recent Stories

An FCPS employee gets vaccinated against COVID-19 at an Inova clinic in January 2021 (photo by Karen Bolt/Fairfax County Public Schools) Fairfax County is looking for artists to contribute to…

Reston Association (courtesy RA) Reston Association’s Board of Directors filled an at-large seat vacated by board member Glenn Small in November.  At a Thursday (Jan. 26) night meeting, the board…

The county’s housing authority has entered into an agreement with Foulger-Pratt (Photo via Fairfax County). A task force will discuss the redevelopment of Reston Town Center North (RTC North) beginning…

Morning Notes

Vehicles turn off Route 123 into Tysons Corner Center (staff photo by Angela Woolsey) Vienna’s Ilia Malinin Impresses at U.S. Skating Championships — “Even before his leading score of 110.36…

The Ravel Dance Studio will re-open for fall classes 2020. The school will offer in person and virtual online instruction. With over 5000 sq. ft. to social distance the school has added air ionization filtration systems, ballet barres, acrylic dividers, hands free bathrooms, strict monitoring and more.

The Ravel Dance Studio will produce a Nutcracker Ballet Hollywood style video through the Reston Community CenterStage. REGISTRATION online begins August 17.

Submit your own Community Post here for just $99.

Chris Green is one of the DMV’s finest fitness instructors. A Lululemon and South Block ambassador, he is a coach and mentor to so many. He embodies grace, positivity and motivation in ways that no one else can. If we could all learn a thing or two from him, the world would be a much better place. He does so much for others, and does so with a smile on his face 99% of the time.

He recently ruptured his Achilles and has an incredibly long and tough journey ahead. As if COVID hadn’t impacted fitness professionals enough, throw this in the mix and it’s a double, even triple whammy. CG is no longer able to work and do what he loves for the time being because of this and we’d love your support.

Read More

Submit your own Community Post here for just $99.

×

Subscribe to our mailing list