Anticipated Silver Line Phase 2 delay leaves Metro treading water

The Herndon Metro station (staff photo by Jay Westcott)

The Labor Day deadline for “substantial completion” of Silver Line Phase 2 won’t be met, Metro staff acknowledged at a Board of Directors safety and operations committee meeting today (Thursday).

The presentation confirmed what the Metropolitan Washington Airports Authority (MWAA) told Fairfax County earlier this month.

At this point, it remains unknown when the project will be substantially completed and able to be turned over to the Washington Metropolitan Area Transit Authority (WMATA). The expected delay will likely push the opening date even further back.

“There hasn’t been a new substantial completion day published [by MWAA],” said Andy Off, Metro’s vice president of project implementation and construction. “But we are confident it’s going to get moved past Labor Day.”

The latest delay of the $2.8 billion public transportation project stems from the need for more testing and work to tie Silver Line’s first and second phases together. That will require another shutdown of Wiehle-Reston East Metro station, much like the one that happened late last month.

“There are specific tests that were not completed over that weekend that necessitated a further shutdown,” Off said. “We are currently working with MWAA to schedule that.”

Reston Now reached out to MWAA about when that station shutdown will happen but has to hear back as of publication.

Off assured committee members that the delay has nothing to do with concrete issues or any other major safety concern.

“Right now, it’s really an IT project as it relates to our signal infrastructure,” Off said.

Once the Wiehle-Reston East outage gets scheduled and the work is completed, Off said there will be a better idea of a substantial completion date, with “fall” being as specific as he can get at this juncture.

Metro will need about six months from substantial completion to complete testing and “pre-revenue activities,” including trainings and further testing, which is contractually obligated to take no longer than 90 days, according to a presentation to Fairfax County Board of Supervisors transportation committee last month.

A Labor Day hand-off would have put Silver Line Phase 2 on track to open in the first quarter of 2022, but now, operations likely won’t begin until later that year. The project will extend Metro from Reston into Loudoun County with six new stations.

At the WMATA board committee meeting, officials emphasized that this delay is unrelated to any problem. There’s simply a need for more testing time.

“It’s not unusual to have several tests planned and just not have the amount of time as you need,” rail safety expert Devin Rouse, who’s on the Metro board, said. “If anything significant does come up, that’s a discussion we really need to have. At this point, this is normal for these types of projects.”

While officials have downplayed this particular delay, it follows a long line of Silver Line Phase 2 holdups that have frustrated residents and businesses waiting for the multi-billion-dollar public transporation project, which was initially set to open in 2018.

Recent Stories

Marc Smith will serve as the new Herndon economic development director starting in May (courtesy Town of Herndon) The Town of Herndon is getting a new director of economic development….

Morning Notes

Reston (staff photo by Scott Brodbeck) Demolition begins at burned hust of Oud Resto and Hall — “The site of the Main Street restaurant that burned down in 2020 is where…

OmBaked CBD Boutique at Lake Anne Plaza in Reston (staff photo by James Jarvis) OmBaked CBD Boutique at Lake Anne Plaza in Reston is hosting a holistic health fair next…

Morning Notes

Boaters and geese can be seen in the distance on Lake Accotink (staff photo by Angela Woolsey) Man fires gun at dog, Fairfax County police say — “Fairfax County Police…

×

Subscribe to our mailing list