The eastbound Dulles Access Highway (DIAAH) will be closed between Centreville Road and Fairfax County Parkway from Friday (August 3) at 10 p.m. through Monday (August 6) at 5 a.m.

Traffic from the eastbound lanes will be diverted to the left lane of the eastbound Dulles Toll Road and will then be returned to the DIAAH once past the construction area. The closure is necessary to allow Dulles Corridor Metrorail Project crews to complete storm drain work in the area.

DIAAH drivers will not have to pass through any toll both on the toll road during the detours. Eastbound toll road traffic will be restricted to two lanes. All drivers are strongly encouraged to exercise caution and pay attention to all signs and barricades.

Map via Dulles Corridor Metrorail Project

0 Comments

Beginning tomorrow (July 12) and on Friday night (July 13), triple lane closures on planned on the Dulles Toll Road after 10 p.m.

Dulles Corridor Metrorail Project crews will continue to install equipment under the pedestrians bridges at the Reston Town Center and Herndon Metrorail Stations that cross over the eastbound and Westbound lanes of the Dulles Toll Road.

Three lanes will be closed, resulting in 20-minute traffic halts after midnight each night.

Beginning Thursday at 10 p.m., three left lanes of the eastbound Dulles Toll Road will be closed to traffic between the Monroe/Van Buren Street and Reston Parkway overpasses. One right lane will be open to traffic and 20-minute stoppages will occur in the right lane of the eastbound lanes after midnight. Lanes will reopen on Friday at 5 p.m.

On Friday at 10 p.m., the three left lanes of the westbound Dulles Toll Road will be closed to traffic between the Wiehle Avenue and the Monroe Street/Van Buren Street overpasses. One right lane will be open to traffic and 20-minute stoppages are planned after midnight on the right westbound lane and on the ramp from Fairfax County Parkway to the westbound Dulles Toll Road lanes.

Normal operations will resume on Saturday (July 14) at 6 a.m. Utility work is expected to continue through July.

Maps via Dulles Corridor Metrorail Project

2 Comments

Crews will continue to perform utility work on Centreville Road near the Dulles Toll Road overpass in Herndon through Friday (July 13).

Alternating left and right lane closures on northbound and southbound Centreville Road and along the ramp from the westbound Dulles Toll Road lane to northbound Centreville Road and Elden Street will also take place.

Work is scheduled to take from today through Thursday from 9:30 a.m. to 3:30 p.m. and on Friday from 9:30 a.m. to noon.

Access to businesses and ramps will remain open while maintenance work continues. Drivers are encouraged to exercise caution and pay attention to all signs and barricades.

Large, slow vehicles will exit and enter roads in the area throughout the day.

Map via Dulles Corridor Metrorail Project

0 Comments

The right lane of Reston Parkway at the intersection of Sunrise Valley Drive will be closed for parts of the week.

Dulles Corridor Metrorail crews will complete drill testing related to the traffic signal.

Closures will remain in effect today (April 23) through Thursday (April 26) from 9:30 a.m. to 3:30 p.m. and on Friday (April 27) from 9:30 a.m. to noon.

Drivers should pay attention to all signage and traffic barriers, as large, slow vehicles may exit and enter the highway at various times throughout the week.

Map via Dulles Corridor Metrorail Project

10 Comments

Prepare for overnight closures on of Sunset Hills Road from Sunday through Thursday from 10 p.m. to 5 a.m.

The eastbound lanes of Sunset Hills Road near the intersection of Town Center Parkway will be closed. The westbound lane of the road will be reduce to one right thru lane as two-way traffic runs through the area.

The lane closure is necessary as construction crews working on the Dulles Corridor Metrorail Project deliver large, heavy equipment to a nearby power substation that will power the future Reston Town Center station on the Silver Line. A crane will place the items on the south side walk.

Police will remain on site and plan to direct eastbound traffic onto the right westbound lane.

Here’s more from the Metropolitan Washington Airports Authority:

Beginning at 10 p.m. each night, eastbound Sunset Hills Road traffic will be diverted to westbound Sunset Hills Road at the intersection of Town Center Parkway.

Westbound Sunset Hills Road will be separated by traffic control devices (i.e. cones or drums) to safely facilitate two-way flow of traffic.

Eastbound Sunset Hills Road will be closed east of the detour.

A crane will be positioned on the south sidewalk and the sidewalk will be closed in this location.

The detour will end just west of Reston Parkway.

No later than 5 a.m. each morning, Sunset Hills Road will be returned to normal traffic flow; however, the crane will remain in place and the sidewalk will remain closed until work is completed.

All plans are subject to change due to weather.

Photo via MWAA

0 Comments

Plans to extend Soapstone Drive could move forward as Fairfax County officials seek public comment tonight on the project, which would create an additional crossing on the Dulles Toll Road for cars, pedestrians and cyclists.

At Dogwood Elementary School (12300 Glade Drive) from 6:30 – 8:30 p.m., the floor will be open for the public to comment on a environmental assessment completed as part of a multi-step process since the Board of Supervisors approved the project in 2014. The study examines the potential effects of the project for properties listed in or eligible for the National Register of Historical Places, the country’s official list of historic sites worthy of preservation.

The new roadway will provide a half-mile extension between Sunrise Valley Drive and Sunset Hills Road and a new crossing over the Dulles Corridor. County officials have said the project is necessary to tackle congestion on Wiehle Avenue, limited access for buses to Wiehle-Reston East Station and the lack of connectivity for pedestrians and bicyclists in the area.

Completed in August, the assessment reviews impacts of the project on surrounding land. For example, the assessment finds the project rests within 200 feet of on two sites with hazardous materials and would result in increased noise for two areas near the project.

Overall, the assessment concludes the project will not “contribute substantially to cumulative impacts, particularly in light of the efforts to minimize adverse impacts of the project and other mitigation measures to be implemented.”

Following the public hearing, the county will revise the assessment as needed and submit it to the Federal Highway Administration, the body which will make a decision about the feasibility of the project.

In 2014, the county’s supervisors included $2.5 million for the preliminary design of this project as part of its Six Year Transportation Project Priorities. At that time, they also put the project — estimated to cost $91.75 million — on the county’s list of high-priority projects for 2015-20.

More information on the project is available on the county’s website. Written or oral comments may be submitted at the hearing or in writing within 10 days after the hearing to [email protected]. Include “Soapstone Connector” in the subject line.

24 Comments

If you’ve traveled down Sunset Hills Road or the Dulles Toll Road recently, you may have noticed the north-side pedestrian bridge for the future Reston Town Center Metro station has been installed.

Once construction is complete, the hulking structure will allow pedestrians to access the Silver Line station from the north side of the Dulles Toll Road and Dulles Airport Access Highway, according to information provided by the Dulles Metrorail Corridor Project.

The installation took place in the late-night hours of Oct. 13-14.

Construction work on Phase 2 of the Silver Line, which will extend the Metrorail from Reston to Ashburn, was reported earlier this month to be about two-thirds done. The line is expected to be opened to the public in 2020.

Photos courtesy Dusty Smith/Dulles Corridor Metrorail Project

2 Comments

As work on Phase 2 of Metro’s Silver Line project continues, a pedestrian walkway was recently set over the bus loop at the Herndon-Monroe Park and Ride facility.

The walkway, which will provide access to the Silver Line’s future Herndon Station from the south side of the Dulles Toll Road, will be integrated with existing and future infrastructure at the park and ride, according to information provided by the Dulles Corridor Metrorail Project.

The pedestrian bridge from the north side of the Dulles Toll Road (westbound lanes) is scheduled to be installed this weekend.

Construction work on Phase 2 of the Silver Line, which will extend the Metrorail from Reston to Ashburn, was reported in July to be more than 60 percent done. The line is expected to be opened to the public in 2020.

Photos courtesy Dusty Smith/Dulles Corridor Metrorail Project

2 Comments

Friday Morning Notes

Toll Road Traffic To Be Affected by Weekend Work — Westbound traffic will be rerouted this weekend as to allow crews to set pedestrian bridges that will provide access over the westbound highways to the Silver Line’s future Herndon station. [Dulles Corridor Metrorail Project]

Volunteers Needed for Watershed Cleanup — Help is needed Saturday at parks around Fairfax County, including locally at Lake Fairfax Park and Frying Pan Farm Park. [Fairfax County Park Authority]

FCPD Officer Pleads No Contest — Officer Pshko Siteki was heading to a call for a disorderly conduct incident in February when his speeding cruiser struck a minivan in the Seven Corners area. [Washington Post]

An Unexpected Stint in the NFL — Thirty years ago this month, South Lakes High School’s wrestling coach became a temporary member of the Washington Redskins during the National Football League players’ strike. John Cowne, who later would become an assistant coach for the SLHS Seahawks football team, remembered that once-in-a-lifetime experience in a recent interview. [Inside NoVa]

2 Comment

Monday Morning Notes

Office of Government Ethics Director Has Reston Roots — In a letter to the editor, John Lovaas salutes Walter Shaub, an SLHS grad. He also commends the Reston Association Board of Directors for its recent work to attend to matters of ethics. [Fairfax Times]

Parking Lot Resurfacing — Resurfacing of the Lake Newport soccer fields parking lot is scheduled to begin today, and the project is anticipated to take three days to complete. The lot will be closed during that time. For further information, email [email protected]. [Reston Association]

Reston-Based Swim Team Sets Records — Members of the Fox Mill Woods Swim Club broke two marks at the Northern Virginia Swim League’s recent All-Star Relay Meet. [Reston Patch]

Toll Road Lane, Ramp Closures — Once again this week, there will be plenty of activity on the Dulles Toll Road, Airport Access Highway and Dulles Greenway as work continues on the Silver Line. [Dulles Corridor Metrorail Project]

2 Comment

Friday Morning Notes

Toll Road Ramp Detour Starts This Weekend — The ramp from the eastbound Dulles Toll Road to the Fairfax County Parkway will be diverted through the Herndon-Monroe Park and Ride parking lot. The detour is expected to remain in place through 2017 to allow Dulles Corridor Metrorail Project crews to perform utility and road work on the ramp. [Dulles Corridor Metrorail Project]

Wombat Hoax Spreads on Twitter — A Twitter account posing as Roer’s Zoofari has been claiming this week that a wombat escaped from the zoo. A lot of people fell for the gag. [Reston Patch]

Trip to Pro Tennis Match Slated — Reston Association will have a group outing Tuesday night to see Martina Hingis and the Washington Kastles face the New York Empire. [Reston Association]

Sobriety Checkpoint Saturday Night — Police departments from Fairfax and Loudoun counties will be working together at a sobriety checkpoint Saturday night from 11 p.m. to 2 a.m. in the Centreville/Chantilly area. [Fairfax County Police Department]

3 Comments

Friday Morning Notes

Vendors Sought for Multicultural Festival — Reston Community Center is seeking arts and crafts vendors, food vendors and civic organizations of all cultures for the 17th annual Reston Multicultural Festival. The festival will be held Saturday, Sept. 23 at Lake Anne Plaza. Applications are being accepted through July 28. [Reston Community Center]

Covered Bridge Renovated — In its latest “Reston Today” video dispatch, Reston Association shows off the work that has been done on the covered bridge on the RA trail system near Lake Anne. [Reston Association/YouTube]

Metro Work This Weekend — The Silver Line will only run to Ballston this weekend. In addition, new Metro hours go into effect tonight. The system will close at 1 a.m. Friday and Saturday nights, but is only open from 8 a.m. to 11 p.m. on Sundays. [WTOP]

Toll Road Work Rescheduled — Due to poor weather, the detour diverting traffic heading to the Fairfax County Parkway from the eastbound Dulles Toll Road exit ramp through the Herndon-Monroe Park & Ride north parking lot was canceled last night. It has been rescheduled for Sunday night, July 16. [Dulles Corridor Metrorail Project]

8 Comments

Friday Morning Notes

Weather Report for Holiday Weekend  This Saturday, expect a high near 90 degrees, but a chance of afternoon thunderstorms might impact projected fireworks shows in the area. Sunday, Monday and Tuesday will also have highs in the low 90s, but there’s a chance of rain on the Fourth. [The Weather Channel]

Heavy Congestion Projected on Holiday Weekend  According to the Virginia Department of Transportation’s interactive traffic trends map, expect major traffic jams along Interstate 95 on Sunday as people travel for the holiday. [VDOT]

Residents Reminded to Be Safe With Fireworks  Make sure fireworks are legal in your area before buying or using them, never have any portion of your body directly over a fireworks device when lighting the fuse, never try to re-light or pick up fireworks that have not fully functioned, and never point or throw fireworks at another person. [Fairfax County Fire and Rescue]

New Laws Take Effect Tomorrow — Take a look at some of the new legislation that will go into effect July 1, including changes to rules about absentee voting, concealed carry permits and more. [Fairfax County]

Toll Road Ramp Work Starts After Holiday  Make sure to reevaluate the morning commute starting next next Friday. The ramp from the eastbound Dulles Toll Road to the Fairfax County Parkway will be diverted through the Herndon-Monroe Park and Ride parking lot, starting next Thursday night and lasting “through 2017.” [Dulles Corridor Metrorail Project]

Local Artist Wins Tröegs Contest — Marni Manning’s “Renaissance of Beer” painting was the big winner in the Pennsylvania craft beer company’s recent art contest. [Tröegs]

Herndon Man Admits to Bank Robberies — Bruce Wayne Higgins robbed four banks in Maryland and New Jersey last December. [WTOP]

0 Comments

Friday Morning Notes

Colts Neck Tennis Courts Closed — Drainage work and resurfacing at the courts will have them closed for about a month. [Reston Association/Twitter]

More Work on Toll Road This Weekend — Overnight work is planned tonight through Monday between Fairfax County Parkway and Reston Parkway, as crews continue construction of the Reston Town Center Metrorail station in the median of the Dulles Access Highway. [Dulles Corridor Metrorail Project]

Free Smoothie for National Flip Flop Day — Tropical Smoothie Café (11684 Plaza America Drive) is giving a free Sunshine Smoothie to anyone who comes in wearing flip flops between 2 and 7 p.m. today. Blaire from “The Jack Diamond Morning Show” will be there as well. [Mix 107.3/Twitter]

Teen Star Talks About Growing Up in RestonJacob Sartorius says he faced a lot of bullying in school. The 14-year-old is becoming a sensation, though, with 14 million followers on the app Musical.ly, 7 million followers on Instagram and more than 2 million subscribers to his YouTube channel. [Asbury Park Press]

0 Comments

Monday Morning Notes

Heat Wave Continues — It was hot over the weekend and high temperatures are expected to get into the 90s again for the next couple days. Fairfax County wants residents to be aware of the dangers of extreme heat. [Fairfax County Fire and Rescue/Fairfax County Emergency Information]

Volunteers Still Needed for ‘Taste’ — Organizers of the Taste of Reston, scheduled for this weekend at Reston Town Center, say they are still in need of some volunteers for Friday and Saturday night shifts. [Taste of Reston]

Utility Work Starts Tomorrow Night — Crews will be doing utility relocation work at the main entrance to the Herndon-Monroe Park and Ride, located at the intersection of Sunrise Valley Drive and Roark Street. The work is expected to be take about three weeks. [Dulles Corridor Metrorail Project]