Silver Line Phase 2 Construction is Nearly 76 Percent Complete

Silver Line Phase 2 Construction at Reston Town Center (Photo via Capital Rail Constructors)Construction of Phase 2 of the Silver Line extension into Loudoun County is nearly 76 percent complete, according to a quarterly update by Capital Rail Constructors.

At a Wednesday meeting, the lead contractor on the project told the Metropolitan Washington Airports Authority that the project is on track. By 2020, officials hope to open the second phase of the line, which brings 23 miles of track past Dulles Airport and into Loudoun County.

Precasting work at the Reston Town Center Station will be completed by February. Mechanical, electrical and plumbing outfitting will continue through the fall of this year while roofing will finish by June.

Concrete work has been completed at the North Pavilion and precasting is almost finished. The breakdown of pedestrian bridges, provided by Capital Rail Constructors, is below:

Metal decking at the Herndon Station is complete as work on mechanics, roofing, skylights, elevators and the track continues. The concrete structure and utility work surrounding the South Pavilion has also been completed.

Most workers involved in the project — 58 percent — are from Virginia while 26 percent are from Maryland.

Photos via handout by Capital Rail Constructors

Recent Stories

Live Fairfax is a bi-weekly column exploring Fairfax County. This recurring column is sponsored and written by Sharmane Medaris of McEnearney Associates. Questions? Reach Sharmane at 813-504-4479. Sold by Sharmane and Style by Valentine teamed up…

For this year’s Independent Bookstore Day, local bookworms will be encouraged to collect not just new literary titles, but also places to buy them. More than a dozen shops across…

RELAC Water Cooling will begin delivering air-conditioning services to residents and businesses in Reston’s Lake Anne area this weekend — ahead of its official launch date of May 22. The…

The cost of riding Metro trains and buses will go up, starting July 1, when the transit agency’s new budget takes effect. The Washington Metropolitan Area Transit Authority’s (WMATA) board…

×

Subscribe to our mailing list