The Town of Herndon’s plans for major upgrades to an 0.5-mile stretch from Old Spring Street to Herndon Parkway along Van Buren Street have been delayed.
The project, which would add curb-and-gutter, widen travel lanes to 11 feet, and add bike lanes in each direction, was originally set to be complete by the winter of this year. Now, the timeline is being revised.
Utility relocation, which was originally set to be completed by the end of 2020, will likely take place by March, according to Richard Smith, the town’s engineer on the project. The town is currently working on creating a revising project schedule for all contractors, he said, noting that utility relocation contractors have been delayed for ‘various reasons.
‘This is all contingent on the private contractors completing the relocation and the subsequent authorization by VDOT to allow the town to bid the project for construction,’ Smith told Reston Now in a statement.
Once completed, the project will also relocate overhead utility poles, add crosswalks and signals at Alabama Drive, upgrade stormwater management facilities, and add five-foot-wide sidewalks.
During the construction phase of the project, the town expects the asphalt pedestrian trail along Van Buren Street to be closed to pedestrian and bicycle traffic from Spring Street Park to Aspen Drive.
Originally, the town estimated construction would begin in the fall of 2019 or early winter of 2020.
Photo via handout/Town of Herndon
Recent Stories
Planned facility upgrades will require the Reston Regional Library to close for an extended period this summer. Friday, June 28, will be the last day of public operations for the aging…
A private boat dock on Lake Anne in Reston (staff photo by Angela Woolsey) Sentencing of Driver in Fatal Oakton Crash Delayed — “The sentencing hearing in the manslaughter case of…
Celebree School will have a grand opening for its new Herndon location on Saturday, April 27 (courtesy of Celebree School) A Maryland-based early childhood education company is opening a second…
W&OD Trail in Herndon (staff photo by James Jarvis) The Washington & Old Dominion (W&OD) Trail has reached the half-century mark. The Northern Virginia Regional Park Authority (NOVA Parks) is…