Herndon High School Now in Phase Three of Renovations

With Herndon High School’s phase two renovations now completed, the school has moved to phase three. This includes renovations to the auditorium, music, performing, and fine arts rooms, auxiliary gym, and wrestling and gymnastics room.

All of the work should be completed this summer and be ready for students when they are back in the building full-time next school year, assistant principal Jim Hannon tells Reston Now.

The main gym was part of phase two renovations and that was finished late last year, complete with new bleachers. December, when a limited crowd was allowed to attend a basketball game, was the first time they were used.

Work has moved at a decent clip with students and full staff not in the building due to COVID-19 restrictions.

However, Hannon says it’s been “a little bit of a wash” in terms of construction moving any faster. He says that many of the areas being renovated are in isolated areas anyway and the number of construction workers are more limited to social distancing requirements.

After phase three, renovations will begin on the tennis courts, adding additional parking, stadium press box and concession stand, and the food prep area of the cafeteria. That’s the final phase of renovations that first began more than two years ago.

In all, the renovation project is adding more than 138,000 square feet to the more than five-decade old high school building, expanding it by about a third. It will have a capacity of 2,500 students.

Hannon says that all of that work should be done by summer 2022.

Photo courtesy of Jim Hannon

Recent Stories

Planned facility upgrades will require the Reston Regional Library to close for an extended period this summer. Friday, June 28, will be the last day of public operations for the aging…

Morning Notes

A private boat dock on Lake Anne in Reston (staff photo by Angela Woolsey) Sentencing of Driver in Fatal Oakton Crash Delayed — “The sentencing hearing in the manslaughter case of…

Celebree School will have a grand opening for its new Herndon location on Saturday, April 27 (courtesy of Celebree School) A Maryland-based early childhood education company is opening a second…

W&OD Trail in Herndon (staff photo by James Jarvis) The Washington & Old Dominion (W&OD) Trail has reached the half-century mark. The Northern Virginia Regional Park Authority (NOVA Parks) is…

×

Subscribe to our mailing list