Wiehle Metro station shutdown set for October with possible Silver Line Phase 2 hand-off on the horizon

Wiehle-Reston East Garage (via Fairfax Connector)

The Wiehle-Reston East Metro station will be closed during the weekend of Oct. 23 and 24 so crews can work to connect the first and second phase of the Silver Line.

This will be the second time in six months that the station has been shut down so the two phases can be tied together after work and tests related to signal infrastructure were not completed in June as expected, necessitating another shutdown.

If the work is completed as hoped this time, it will be a major milestone for the $2.8 billion Silver Line Phase 2 project, potentially putting it on track for substantial completion by November.

The scheduled shutdown was added to Washington Metropolitan Area Transit Authority’s (WMATA) track work page shortly after officials delivered an update on the project to the WMATA board yesterday (Thursday).

Metropolitan Washington Airports Authority (MWAA) spokesperson Marcia McAllister said in an email to Reston Now that the scheduling of the shutdown for late October is “great news.”

“Now that a date has been set for the service outage needed to allow completion of the tie-in between Phase 1 and Phase 2 of the Silver Line, the Airports Authority and our contractors can get this essential work done in October and move the project toward substantial completion,” McAllister wrote.

Substantial completion refers to the point when MWAA will be ready to hand the project to WMATA. The authority previously set Labor Day weekend as the deadline but acknowledged in July that it wouldn’t meet that timeline.

At the board meeting, WMATA officials said they were comfortable with MWAA setting a new substantial completion deadline for the end of this year, stating that the work will most likely be finished in November.

If that is the case, Metro will still need another five to six months of operational readiness testing and pre-revenue activities, but that could mean the Silver Line Phase 2 will open to riders by May 2022.

However, in MWAA’s most recent monthly report, the project’s contractor Capital Rail Constructors proposed a substantial date of May 19, 2022, which could push the opening all the way to late 2022. It wasn’t the first time that the two parties disagreed on the project’s schedule.

Shortly after the report was released, though, CRC project executive Keith Couth told Reston Now that there were “opportunities through collaboration” to improve on that date and get it completed much sooner.

When reached for comment, Couch reiterated that they are working to finish by the end of this year.

“We are in the testing phase of the project which is very dependent on coordinating and finalizing testing with MWAA and WMATA, including scheduling of the next outage at Wiehle Avenue and the review of test reports,” Couch said. “In collaboration with MWAA and WMATA, we are working together to improve on the schedule, targeting a substantial completion in Q4.”

With the Wiehle shutdown now scheduled and the contractor supportive of a hoped-for 2021 substantial completion date, Silver Line Phase 2 is seemingly back on track after years of delays that have frustrated local officials, residents, and businesses alike.

“Level F” testing — meaning testing with actual trains — also began late last month and is going well, according to WMATA officials.

The nearly $3 billion project will extend Metro’s Silver Line from the Wiehle-Reston East station west to Ashburn in Loudoun County. In total, six new stations will be added, including one at Reston Town Center and two in Herndon.

Construction began back in 2014 and was originally supposed to finish in 2018.

Photo via Fairfax Connector

Recent Stories

The nonprofit Arlington Partnership for Affordable Housing has proposed two 20-story affordable housing buildings in Dominion Square West, seen from the northeast (via KGD Architecture/Fairfax County) Fairfax County and several…

(Updated at 4:15 p.m.) Developer Foulger-Pratt‘s unsolicited proposal to redevelop Bowman Towne Court in Reston has been scrapped, Fairfax County announced today. In a termination letter, the developer cited “significantly…

This biweekly column is sponsored by The Mather in Tysons, Virginia, a forward-thinking Life Plan Community for those 62 and better. In times of stress, a positive attitude can help you…

Nova Wild — formerly known as Roer’s Zoofari and, before that, Reston Zoo — will partially reopen this weekend with a new self-drive safari. Customers will get the chance to…

The Ravel Dance Studio will re-open for fall classes 2020. The school will offer in person and virtual online instruction. With over 5000 sq. ft. to social distance the school has added air ionization filtration systems, ballet barres, acrylic dividers, hands free bathrooms, strict monitoring and more.

The Ravel Dance Studio will produce a Nutcracker Ballet Hollywood style video through the Reston Community CenterStage. REGISTRATION online begins August 17.

Submit your own Community Post here for just $99.

Chris Green is one of the DMV’s finest fitness instructors. A Lululemon and South Block ambassador, he is a coach and mentor to so many. He embodies grace, positivity and motivation in ways that no one else can. If we could all learn a thing or two from him, the world would be a much better place. He does so much for others, and does so with a smile on his face 99% of the time.

He recently ruptured his Achilles and has an incredibly long and tough journey ahead. As if COVID hadn’t impacted fitness professionals enough, throw this in the mix and it’s a double, even triple whammy. CG is no longer able to work and do what he loves for the time being because of this and we’d love your support.

Read More

Submit your own Community Post here for just $99.

×

Subscribe to our mailing list