Renovations begin on Hook Road tennis courts, to be completed in summer

(Updated, 4:40 p.m.) Reston Association is in the midst of renovating the Hook Road tennis courts on Fairway Drive.

In recent years, the courts have started to crack and show their age, considering they were built in the mid 1970s. The project was first discussed in 2016.

Renovations began in early March and are expected to be completed by late June or early July, though RA Director of Capital Projects Chris Schumaker says that the project is currently ahead of schedule.

In a video update on the renovation, Schumaker explains that RA is doing a “full depth reclamation process” that involves pulling up the existing asphalt, grinding it up, and mixing it with cement so that it can be compacted and laid down as the base for the new tennis court.

On past tennis court projects, RA typically put down a layer of gravel and then added a new layer of asphalt over it, according to Schumaker, but due to the age of the Hook Road courts, which already had several layers of asphalt, they made the decision to instead start over.

By mixing in cement with the asphalt, it should provide a stronger base and make the courts last longer — perhaps as long as 30 to 40 years, Schumaker says.

Reston Association tells Reston Now that the project is estimated to cost $650,000, which also includes refurbishment of the multipurpose court.

The tennis courts renovations are part of a conceptual master plan for Hook Road recreational facilities that includes baseball field upgrades and pathway renovations.

Those portions of the project remain in the “engineering phase,” according to Schumaker.

Back in 2017, tempers flared at several meetings about the Hook Road project. It was related to then-RA Board of Directors Member Ray Wedell’s adamant disagreement with the project and confrontational tactics in expressing them. He subsequently resigned from the board.

Photo via Reston Association/Youtube

Recent Stories

Live Fairfax is a bi-weekly column exploring Fairfax County. This recurring column is sponsored and written by Sharmane Medaris of McEnearney Associates. Questions? Reach Sharmane at 813-504-4479. Sold by Sharmane and Style by Valentine teamed up…

For this year’s Independent Bookstore Day, local bookworms will be encouraged to collect not just new literary titles, but also places to buy them. More than a dozen shops across…

RELAC Water Cooling will begin delivering air-conditioning services to residents and businesses in Reston’s Lake Anne area this weekend — ahead of its official launch date of May 22. The…

The cost of riding Metro trains and buses will go up, starting July 1, when the transit agency’s new budget takes effect. The Washington Metropolitan Area Transit Authority’s (WMATA) board…

×

Subscribe to our mailing list